-
计划风险管理中英文对照外文翻译文献
计划风险管理中英文对照外文翻译文献
(
文档含英文原文和中文翻译
)
原文:
Schedule Risk Management
INTRODUCTION
Schedule risks are both threats and
opportunities to the success of a project.
Threats
tend
to
reduce
the
success
of
meeting
the
project
goals
and
opportunities tend to increase the
success. Risk management is the process of
identifying, analyzing, qualifying and
quantifying the risks, and developing a
plan
to
deal
with
them.
This
is
routinely
done
during
baseline
schedule
development
as
well
as
during
schedule
updates.
Implementation
of
risk
.
.
1
计划
风险管理中英文对照外文翻译文献
management
starts with early planning in both budgetary cost
estimating and
preliminary
master
scheduling
in
order
to
determine
budgets
and
schedules
with a comfortable level of confidence
in the completion date and final cost.
While there are entire volumes
addressing risk in construction projects, it is
important to note that the issue of
time-related risk has not been universally
incorporated
into
planning.
Assessing
cost
risk
is
more
intuitive,
and
very
often
addressed
through
the
use
of
heuristics,
so
it
has
become
more
of
a
standard of
the industry than time-related risk management.
Most estimators
will automatically add
a contingency to
a cost estimate to
cover the risk of performance based on the type of
project
and
circumstances
pertaining
to
the
undertaking
of
the
project.
Estimators
estimate
this
contingency
using
their
own
rules
of
thumb
developed
over
years
of
estimating
as
well
as
estimate
ingmanuals
,
such
as
Means’
Cost
Data or Cost Works.
However, when it comes to
developing
the
critical
path
method
(CPM)
schedules,
risk
management
is
often overlooked or underestimated.
The purpose of this chapter is to
provide an overview of risk management
and the assessment process as well as
best practices for incorporation of risk
management
into
CPM
schedule
development
and
maintenance.
For
more
detailed
information
about
schedule
risk,
the
reader
should
refer
to
risk
management books, particularly those
that focus on project management. One
of the best resources available is
David Hulett
’s
new book,
Practical Schedule
.
.
2
计划风险管理中英文对照外文翻译文献
Risk Analysis.
Any
risk
management
program
starts
with
a
good
and
accurate
CPM
schedule,
created
through
the
use
of
best
practices
and
checked
for
quality,
reasonableness,
and
appropriateness
of
the
network
model.
Without
a
well-designed
and
developed
CPM
baseline
schedule,
a
risk
management
process
will
not
be
effective.
The
risk
analysis
depends
upon
accurate
and
consistent
calculations
of
the
network
logic,
the
appropriateness
of
the
sequencing
and
phasing,
and
a
reasonable
approach
to
estimating
activity
durations.
Most CPM
schedules are not adjusted for risk but rather are
developed as
if there
were
one right answer for the schedule’s numerical
data. Generally,
activity
durations
are
established
by
calculation
of
the
quantity
of
work
represented
by
an
activity
divided
by
the
production
rate,
or
by
sheer
‘‘gut
feeling’’
of
the
project
manager
or
crew
leader.
This
production
rate
is
normally
established
by
the
contractor’s
historical
records
or
an
estimating
system,
such
as
Means’,
that
provides
an
accurate
data
base
of
average
production rates.
Once those durations are calculated, they are
often used as
deterministic
values,
which
assumes
that
the
durations
are
accurate
and
unlikely
to
change.
This
assumption
ignores
the
fact
that
the
schedule
is
attempting
to
predict
how
long
it
will
take
to
complete
an
activity
at
some
unknown time in the future,
using an unknown crew composition, with
variable experience, and working
.
.
3
计划
风险管理中英文对照外文翻译文献
in
unknown
conditions.
Risk
management
recognizes
the
uncertainty
in
duration estimating and provides a
system to brain storm other risks that may
occur during the project. Probability
distributions are the best way to model
planned activity
durations,
as noted by Hulett ‘‘The best way to understand
the
activity
durations
that
are
included
in
the
schedule
is
as
probabilistic
statements
of
possible
durations
rather
than
a
deterministic
statement
about
how long the future
activity will take.’’
DEFINITION OF RISK TERMS
The Project Management Institute (PMI)
defines project risk in its Project
Management
Body
of
Knowledge
(PMBOK)
as
‘‘an
uncertain
event
or
condition
that,
if
it
occurs,
has
a
positive
or
negative
effect
on
at
least
one
project objective, such
as time, cost, scope, or quality. A risk may have
one or
m
ore
causes
and,
if
it
occurs,
one
or
more
impacts.’’
PMBOK
adds
‘‘Risk
conditions
could
include
aspects
of
the
project’s
or
organization’s
environment
that
may
contribute
to
project
risk,
such
as
poor
project
management
practices, or dependency on external participants
who cannot be
controlled.’’
Risk Management: A process
designed to examine uncertainties occurring
during
project
delivery
and
to
implement
actions
dealing
with
those
uncertainties
in
order
to
achieve
project
objectives
The
definition
of
risk
management in PMBOK,
4th Edition, is: ‘‘systematic
process
of identifying,
analyzing, and
responding to project risk.’’
.
.
4<
/p>
计划风险管理中英文对照外文翻译文献
Risk definition by AACEi Cost
Engineering Terminology7 is: ‘‘the degree
of
dispersion
or
variability
around
the
expected
or
‘best’
val
ue,
which
is
estimated to
exist
for
the
economic
variable
in question,
e.g.,
a quantitative
measure of the upper and lower limits
which are considered reasonable for the
factor being estimated.’’
Time
Contingency:
An
amount
of
time
added
to
the
base
estimated
duration to allow
for unknown impacts to the project schedule, or to
achieve a
certain level of confidence
in the estimated duration.
Probability:
A measure of the likelihood of occurrence of an
event.
Risk
register:
A
checklist
of
potential
risks
developed
during
the
risk
identification phase of risk
management.
Risk
allocation:
A
determination
of
how
to
respond
to
risks,
which
can
include
shifting
risk,
avoiding
risks,
preventing
or
eliminating
risks,
and
incorporating risks into
the schedule.
Deterministic: A
calculated approach to estimating single activity
duration
using work quantity divided by
estimated production rate.
Probabilistic:
The
determination
of
risk
likelihood
and
consequences
to
establish
duration
ranges
or
risk-adjusted
durations
that
can
be
used
in
a
schedule
in
recognition
that
there
are
no
certainties
in
estimating
future
durations.
Monte Carlo
analysis: A probabilistic approach to determining
confidence
levels of completion dates
for a project schedule by calculating durations as
.
.
5<
/p>
计划风险管理中英文对照外文翻译文献
probability distributions.
Probability distribution: The spread of
durations in a statistically significant
population that is used for the range
of durations in probabilistic scheduling
approaches.
Confidence
level: A measure of the statistical reliability of
the prediction of
project completion.
What-if scenario: A modeling of a risk
for use in a CPM schedule in order
to
predict the ramifications of an identified risk.
Qualitative
analysis:
Occurring
on
the
project,
as
well
as
assessing
the
severity of that risk should it occur
and prioritizing the resultant list of risks.
Quantitative
analysis:
The
assigning
of
a
probability
to
the
qualitative
description of the risk, ranking the
risks, and calculating the potential impact
from
both
individual
risks
as
well
as
the
cumulative
effect
of
all
risks
identified.
Exculpatory clauses: Disclaimer
verbiage that is designed to shift risk.
TYPES OF RISK IN
CONSTRUCTION PROJECTS
Everything that
has ever gone wrong on a construction project is a
potential
risk
on
the
next
project.
Many
project
managers
instinctively
develop
a
lessons-learned
list
of
historical
risks
and
take
steps
to
minimize
their
exposure to those
risks in the future.
Risks vary by
industry and even by construction project type as
well as by
personnel
involved
with
the
project.
A
roadway
or
bridge
project
has
a
.
.
6<
/p>
计划风险管理中英文对照外文翻译文献
different group of risks than a
facility or building, and the selected contractors
may have different degrees of influence
on the level of risks to performance.
If an owner attempts to save money in
preconstruction services by limiting the
extent of field investigation or
development of as-built data, there will be a
higher
risk
of
discovery
of
unknown
problems.
The
experience
and
competence of the
architects and engineers handling the design of
the project,
as well as their quality
control in
development of working
drawings, directly affect the construction effort
and,
consequently, the risk associated
with the plans and specifications.
Even
if the owner has been proactive in preconstruction
investigation, there is
always a risk
of unforeseen conditions. This can be a function
of the type of
soils
encountered,
the
local
municipality,
and
its
culture
and
history
of
keeping good records of obsolete
utilities. If the city in which the project is to
be
built
has
a
history
of
requiring
contractors
to
remove
all
abandoned
underground lines,
there is a much lower risk of underground
conflicts.
The
selection
of
the
project
team
can
impact
positively
or
negatively
the
probability
of
successful
project
completion.
Design-bid-build
projects
that
use
procurement philosophies allowing all financially
capable contractors to
participate
will
likely
experience
a
much
higher
level
of
risk
to
on-time
performance
than
a
procurement
philosophy
that
requires
qualification
of
proposed contractors to
ensure that they have the appropriate experience
and
resources to construct the project.
A single weak subcontractor on a project
.
.
7<
/p>
计划风险管理中英文对照外文翻译文献
will increase risk of performance and
require more management than may be
anticipated.
If
this
is
not
considered,
everyone
will
be
surprised
when
that
subcontractor
fails
and
has
to
have
their
work
augmented
or
corrected.
Problems
related
to
the
management
and
possible
termination
of
a
failing
subcontractor usually has serious
negative impacts on the project.
The
reputation of the construction manager (CM) as
well as the corporate
culture
will
affect
project
performance.
If
the
CM
defines
success
with
minimum
time
extensions
as the
only
benchmark,
there
will likely
be
more
conflict
and
a
higher
need
for
dispute
resolution
efforts.
In
addition,
the
management
abilities
of
the
CM
directly
affect
many
project
tasks,
such
as
review of shop drawings and response to
requests for information in order to
resolve questions about the
construction.
Work by outside or third
parties can carry significant risks of influence
on
the
project’s success.
For example, a light rail station to be built on
top of a
parking
garage
under
construction
by
a
different
contractor
will
run
an
increased
risk of completion on time. The project has no
control over
—
and
little
ability
to
influence
—
the
completion
of
the
parking
garage,
which
quickly becomes vital
to completion of the light rail project.
Most
projects
are
affected
by
local
weather
conditions,
which,
when
adverse,
can
significantly
impede
progress.
Most
specifications
require
the
contractor
to
take
into
account
the
normal
local
weather
conditions
in
his
schedule
planning, which includes normal adverse weather,
but also allow for
.
.
8
计划风险管理中英文对照外文翻译文献
time extensions when unusually
adverse weather occurs. Best practices would
require the contractor to research the
local historical weather records in order
to plan for three to five year average
weather conditions. Different parts of the
country
and
the
world
have
a
wide
variance
in
weather
conditions,
so
planning or failure to
plan for the risk of local weather can
significantly affect
project success.
Local
political
situations,
especially
in
volatile
political
climates,
may
hamper
all
efforts
to
construct
a project
efficiently.
Countries
with
unstable
political
or
economical
systems
will
have
higher
risks
in
successful
project
completion than those with more stable
systems. Countries or regions subject
to wars, terrorism, turmoil, or other
types
of violence also run greater
risks to successful project completion than
others.
If the locality has a policy of
requiring deep investigation into environmental
issues or stringent or complicated
bureaucracy, projects built in that locality
will have a higher risk of late permits
and conflict during construction.
Another
large
risk
on
any
project
is
the
experience
and
reputation
of
the
project
team
for
safe
construction
practices.
Safety
violations
and
accidents
can shut down a
job completely. Even minor safety failures can
distract the
project team and impede
timely performance. If a contractor has a poor
safety
record, the risk of delays
because of safety violations is increased and
should
be taken into account during
schedule development.
A
large volume
of
change
orders on
a project
will
affect
employee
morale;
.
.
9
计划风险管理中英文对照外文翻译文献
there
is
nothing
worse
than
asking
a
craftsman
to
rip
out
recently
installed
high-quality
woodwork for a requested change. If the CM has a
good change
management program in
place, including most importantly good planning,
the
risks
of
negative
pressure
from
changes
are
lowered.
Without
the
program,
the
risks
may
be
significant
enough
to
derail
project
completion.
Most
conversations
about
risk
are
related
to
negative
risks
that
impair
successful
performance,
but
often
there
are
opportunities
that
would
be
overlooked
without good risk
assessment. A renovation project that calls for a
three-story
masonry wall to be
demolished to the foundation in order to install a
beam
and column system might be
redesigned with a pin beam temporary support
structure, allowing the upper two
stories to remain in place, saving time and
money, as well as removing some risk.
The brainstorming about risks needs to
include looking for opportunities that
could positively impact the project time
for completion.
It seems
obvious that failure to plan for the myriad of
risks that often affect
project
performance
will
render
the
planning
less
accurate.
Without
risk
management, every item
that might appear on a risk register (a checklist
of
potential
risks)
is
a
surprise
to
the
project
team
should
it
happen,
diverting
attention and emphasis from the project
management and consuming valuable
resources. Most disputes arise from
risks that likely were not considered at the
inception
of
the
project
and
might
have
been
eliminated
or
mitigated
with
good risk planning.
.
.
10
计
划风险管理中英文对照外文翻译文献
Once
a
company
develops
a
regular
risk
management
culture,
the
risk
register
generates many of the same risks on project after
project. However, a
company’s
‘‘risk
register’’ should not
be a fixed template, used as is on all its
projects. The list must be updated and
customized for each project taking into
consideration its own risks. These
lessons learned, when incorporated into the
project schedule through the risk
management
program,
are
invaluable
in
helping
to
minimize
threats
that
carry
negative
impacts
and
take
advantage
of
opportunities
that
bring
positive
impacts
to
project comp.
IMPORTANCE OF GOOD PLANNING FOR RISK
MANAGEMENT
The
quality of the risk management plan will control
the usefulness of the
risk
analysis.
This
quality
is
achieved
through
developing
a
good
and
encompassing
master
risk
register
in
a
brainstorming
workshop
with
experienced
attendees,
and
following
that
process
with
analysis
and
risk
allocation.
This
is
combined
with
a
process
of
continuing
risk
monitoring
during updates as
well as continuous cycles of risk management.
Participants
in
the
workshop
will
often
comment
that
they
cannot
take
certain risks into
account because they do not have control of the
risks or they
have
no
idea
if
that
risk
will
actually
happen.
One
of
the
typical
issues
is
repeated
cycles
of
shop
drawings,
where
experience
tells
us
that
a
complicated design may
cause structural steel shop drawings to be
rejected,
requiring
revision
and
resubmission.
Some
stakeholders
feel
that
this
is
.
.
11
计划风险管理中英文对照外文翻译文献
< br>
beyond
their
ability
to
plan
for
and
therefore,
the
schedule
should
ignore
it
and
assume the risk will not happen. Accepting this
assumption minimizes the
risk
identification and analysis process. This type of
risk should be identified,
and then
during the qualitative analysis, it will be weeded
out as a low priority
or incorporated
as a high priority. However, if the risk is just
not included on
the risk register, the
opportunity to analyze it is lost.
With
a thorough and organized risk workshop, based on a
good master risk
register,
and
participation
by
the
major
stakeholders
as
well
as
the
project
management
team,
the
output
of
the
risk
analysis
will
be
very
useful.
The
most likely risks will be identified
and analyzed, and with the rest of the risk
management
steps,
the
schedule
will
evolve
into
a
risk-adjusted
schedule,
capable of reasonable analysis and
realistic completion predictions.
RISK
SHIFTING IN CONTRACTS
Contract language may have a
significant impact on how much of the risk
each
party
carries.
Sometimes
called
exculpatory
clauses,
this
language
attempts to shift
or apportion undetermined risk. Contracts are
often used to
control
or
assign
risk
to
various
parties, or
just to
assign it
to
a
party
other
than
the
owner.
Many
owners,
developers,
and
contractors
prefer
using
standard contract forms, such as those
specially developed by organizations
such
as
the
American
Institute
of
Architecture
(AIA),
the
Construction
Management
Association of America (CMAA), and the
Associated
General
Contractors
(AGC)
in
the
United
States
and
FIDIC
or
.
.
12
-
-
-
-
-
-
-
-
-
上一篇:翻译精选
下一篇:公司管理系统部门英文缩写简称收集