关键词不能为空

当前您在: 主页 > 英语 >

计划风险管理中英文对照外文翻译文献

作者:高考题库网
来源:https://www.bjmy2z.cn/gaokao
2021-02-11 21:04
tags:

-

2021年2月11日发(作者:kuba)


计划风险管理中英文对照外文翻译文献





计划风险管理中英文对照外文翻译文献





(


文档含英文原文和中文翻译


)




原文:




Schedule Risk Management


INTRODUCTION



Schedule risks are both threats and opportunities to the success of a project.


Threats


tend


to


reduce


the


success


of


meeting


the


project


goals


and


opportunities tend to increase the success. Risk management is the process of


identifying, analyzing, qualifying and quantifying the risks, and developing a


plan


to


deal


with


them.


This


is


routinely


done


during


baseline


schedule


development


as


well


as


during


schedule


updates.


Implementation


of


risk



.


.


1


计划 风险管理中英文对照外文翻译文献



management starts with early planning in both budgetary cost estimating and


preliminary


master


scheduling


in


order


to


determine


budgets


and


schedules


with a comfortable level of confidence in the completion date and final cost.


While there are entire volumes addressing risk in construction projects, it is


important to note that the issue of time-related risk has not been universally


incorporated


into


planning.


Assessing


cost


risk


is


more


intuitive,


and


very


often


addressed


through


the


use


of


heuristics,


so


it


has


become


more


of


a


standard of the industry than time-related risk management. Most estimators


will automatically add a contingency to


a cost estimate to cover the risk of performance based on the type of project


and


circumstances


pertaining


to


the


undertaking


of


the


project.


Estimators


estimate


this


contingency


using


their


own


rules


of


thumb


developed


over


years


of


estimating


as


well


as


estimate


ingmanuals




such


as


Means’


Cost


Data or Cost Works. However, when it comes to


developing


the


critical


path


method


(CPM)


schedules,


risk


management


is


often overlooked or underestimated.


The purpose of this chapter is to provide an overview of risk management


and the assessment process as well as best practices for incorporation of risk


management


into


CPM


schedule


development


and


maintenance.


For


more


detailed


information


about


schedule


risk,


the


reader


should


refer


to


risk


management books, particularly those that focus on project management. One


of the best resources available is David Hulett


’s


new book, Practical Schedule



.


.


2


计划风险管理中英文对照外文翻译文献



Risk Analysis.


Any


risk


management


program


starts


with


a


good


and


accurate


CPM


schedule,


created


through


the


use


of


best


practices


and


checked


for


quality,


reasonableness,


and


appropriateness


of


the


network


model.


Without


a


well-designed


and


developed


CPM


baseline


schedule,


a


risk


management


process


will


not


be


effective.


The


risk


analysis


depends


upon


accurate


and


consistent


calculations


of


the


network


logic,


the


appropriateness


of


the


sequencing


and


phasing,


and


a


reasonable


approach


to


estimating


activity


durations.


Most CPM schedules are not adjusted for risk but rather are developed as


if there


were one right answer for the schedule’s numerical data. Generally,


activity


durations


are


established


by


calculation


of


the


quantity


of


work


represented


by


an


activity


divided


by


the


production


rate,


or


by


sheer


‘‘gut


feeling’’


of


the


project


manager


or



crew


leader.


This


production


rate


is


normally


established


by


the


contractor’s


historical



records


or


an


estimating


system,


such


as


Means’,


that


provides


an



accurate


data


base


of


average


production rates. Once those durations are calculated, they are often used as


deterministic


values,


which


assumes


that


the


durations


are


accurate


and


unlikely


to


change.


This


assumption


ignores


the


fact


that


the


schedule


is


attempting


to


predict


how


long


it


will


take


to


complete


an


activity


at


some


unknown time in the future,


using an unknown crew composition, with variable experience, and working



.


.


3


计划 风险管理中英文对照外文翻译文献



in


unknown


conditions.


Risk


management


recognizes


the


uncertainty


in


duration estimating and provides a system to brain storm other risks that may


occur during the project. Probability distributions are the best way to model


planned activity


durations, as noted by Hulett ‘‘The best way to understand


the


activity


durations


that


are


included


in


the


schedule


is


as


probabilistic


statements


of


possible


durations


rather


than


a


deterministic


statement


about


how long the future activity will take.’’



DEFINITION OF RISK TERMS



The Project Management Institute (PMI) defines project risk in its Project


Management


Body


of


Knowledge


(PMBOK)


as


‘‘an


uncertain


event


or


condition


that,


if


it


occurs,


has


a


positive


or


negative


effect


on


at


least


one


project objective, such as time, cost, scope, or quality. A risk may have one or


m


ore


causes


and,


if


it


occurs,


one


or


more


impacts.’’


PMBOK


adds


‘‘Risk


conditions


could


include


aspects


of


the


project’s


or


organization’s



environment


that


may


contribute


to


project


risk,


such


as


poor


project


management practices, or dependency on external participants who cannot be


controlled.’’




Risk Management: A process designed to examine uncertainties occurring


during


project


delivery


and


to


implement


actions


dealing


with


those


uncertainties


in


order


to


achieve


project


objectives


The


definition


of


risk


management in PMBOK, 4th Edition, is: ‘‘systematic


process of identifying,


analyzing, and responding to project risk.’’




.


.


4< /p>


计划风险管理中英文对照外文翻译文献



Risk definition by AACEi Cost Engineering Terminology7 is: ‘‘the degree


of


dispersion


or


variability


around


the


expected


or


‘best’


val


ue,


which


is


estimated to


exist


for


the


economic


variable


in question,


e.g.,


a quantitative


measure of the upper and lower limits which are considered reasonable for the


factor being estimated.’’



Time


Contingency:


An


amount


of


time


added


to


the


base


estimated


duration to allow for unknown impacts to the project schedule, or to achieve a


certain level of confidence in the estimated duration.


Probability: A measure of the likelihood of occurrence of an event.


Risk


register:


A


checklist


of


potential


risks


developed


during


the


risk


identification phase of risk management.


Risk


allocation:


A


determination


of


how


to


respond


to


risks,


which


can


include


shifting


risk,


avoiding


risks,


preventing


or


eliminating


risks,


and


incorporating risks into the schedule.


Deterministic: A calculated approach to estimating single activity duration


using work quantity divided by estimated production rate.


Probabilistic:


The


determination


of


risk


likelihood


and


consequences


to


establish


duration


ranges


or


risk-adjusted


durations


that


can


be


used


in


a


schedule


in


recognition


that


there


are


no


certainties


in


estimating


future


durations.


Monte Carlo analysis: A probabilistic approach to determining confidence


levels of completion dates for a project schedule by calculating durations as



.


.


5< /p>


计划风险管理中英文对照外文翻译文献



probability distributions.


Probability distribution: The spread of durations in a statistically significant


population that is used for the range of durations in probabilistic scheduling


approaches.


Confidence level: A measure of the statistical reliability of the prediction of


project completion.


What-if scenario: A modeling of a risk for use in a CPM schedule in order


to predict the ramifications of an identified risk.


Qualitative


analysis:


Occurring


on


the


project,


as


well


as


assessing


the


severity of that risk should it occur and prioritizing the resultant list of risks.


Quantitative


analysis:


The


assigning


of


a


probability


to


the


qualitative


description of the risk, ranking the risks, and calculating the potential impact


from


both


individual


risks


as


well


as


the


cumulative


effect


of


all


risks


identified.


Exculpatory clauses: Disclaimer verbiage that is designed to shift risk.



TYPES OF RISK IN CONSTRUCTION PROJECTS


Everything that has ever gone wrong on a construction project is a potential


risk


on


the


next


project.


Many


project


managers


instinctively


develop


a


lessons-learned


list


of


historical


risks


and


take


steps


to


minimize


their


exposure to those risks in the future.


Risks vary by industry and even by construction project type as well as by


personnel


involved


with


the


project.


A


roadway


or


bridge


project


has


a



.


.


6< /p>


计划风险管理中英文对照外文翻译文献



different group of risks than a facility or building, and the selected contractors


may have different degrees of influence on the level of risks to performance.


If an owner attempts to save money in preconstruction services by limiting the


extent of field investigation or development of as-built data, there will be a


higher


risk


of


discovery


of


unknown


problems.


The


experience


and


competence of the architects and engineers handling the design of the project,


as well as their quality control in


development of working drawings, directly affect the construction effort and,


consequently, the risk associated with the plans and specifications.


Even if the owner has been proactive in preconstruction investigation, there is


always a risk of unforeseen conditions. This can be a function of the type of


soils


encountered,


the


local


municipality,


and


its


culture


and


history


of


keeping good records of obsolete utilities. If the city in which the project is to


be


built


has


a


history


of


requiring


contractors


to


remove


all


abandoned


underground lines, there is a much lower risk of underground conflicts.


The


selection


of


the


project


team


can


impact


positively


or


negatively


the


probability


of


successful


project


completion.


Design-bid-build


projects


that


use procurement philosophies allowing all financially capable contractors to


participate


will


likely


experience


a


much


higher


level


of


risk


to


on-time


performance


than


a


procurement


philosophy


that


requires


qualification


of


proposed contractors to ensure that they have the appropriate experience and


resources to construct the project. A single weak subcontractor on a project



.


.


7< /p>


计划风险管理中英文对照外文翻译文献



will increase risk of performance and require more management than may be


anticipated.


If


this


is


not


considered,


everyone


will


be


surprised


when


that


subcontractor


fails


and


has


to


have


their


work


augmented


or


corrected.


Problems


related


to


the


management


and


possible


termination


of


a


failing


subcontractor usually has serious negative impacts on the project.


The reputation of the construction manager (CM) as well as the corporate


culture


will


affect


project


performance.


If


the


CM


defines


success


with


minimum


time


extensions


as the


only


benchmark,


there


will likely


be


more


conflict


and


a


higher


need


for


dispute


resolution


efforts.


In


addition,


the


management


abilities


of


the


CM


directly


affect


many


project


tasks,


such


as


review of shop drawings and response to requests for information in order to


resolve questions about the construction.


Work by outside or third parties can carry significant risks of influence on


the


project’s success. For example, a light rail station to be built on top of a


parking


garage


under


construction


by


a


different


contractor


will


run


an


increased risk of completion on time. The project has no control over



and


little


ability


to


influence



the


completion


of


the


parking


garage,


which


quickly becomes vital to completion of the light rail project.


Most


projects


are


affected


by


local


weather


conditions,


which,


when


adverse,


can


significantly


impede


progress.


Most


specifications


require


the


contractor


to


take


into


account


the


normal


local


weather


conditions


in


his


schedule planning, which includes normal adverse weather, but also allow for



.


.


8


计划风险管理中英文对照外文翻译文献



time extensions when unusually adverse weather occurs. Best practices would


require the contractor to research the local historical weather records in order


to plan for three to five year average weather conditions. Different parts of the


country


and


the


world


have


a


wide


variance


in


weather


conditions,


so


planning or failure to plan for the risk of local weather can significantly affect


project success.


Local


political


situations,


especially


in


volatile


political


climates,


may


hamper


all


efforts


to


construct


a project efficiently.


Countries


with unstable


political


or


economical


systems


will


have


higher


risks


in


successful


project


completion than those with more stable systems. Countries or regions subject


to wars, terrorism, turmoil, or other types


of violence also run greater risks to successful project completion than others.


If the locality has a policy of requiring deep investigation into environmental


issues or stringent or complicated bureaucracy, projects built in that locality


will have a higher risk of late permits and conflict during construction.


Another


large


risk


on


any


project


is


the


experience


and


reputation


of


the


project


team


for


safe


construction


practices.


Safety


violations


and


accidents


can shut down a job completely. Even minor safety failures can distract the


project team and impede timely performance. If a contractor has a poor safety


record, the risk of delays because of safety violations is increased and should


be taken into account during schedule development.


A


large volume


of


change


orders on


a project


will


affect


employee


morale;



.


.


9


计划风险管理中英文对照外文翻译文献



there


is


nothing


worse


than


asking


a


craftsman


to


rip


out


recently


installed


high-quality woodwork for a requested change. If the CM has a good change


management program in place, including most importantly good planning, the


risks


of


negative


pressure


from


changes


are


lowered.


Without


the


program,


the


risks


may


be


significant


enough


to


derail


project


completion.


Most


conversations


about


risk


are


related


to


negative


risks


that


impair


successful


performance,


but


often


there


are


opportunities


that


would


be


overlooked


without good risk assessment. A renovation project that calls for a three-story


masonry wall to be demolished to the foundation in order to install a beam


and column system might be redesigned with a pin beam temporary support


structure, allowing the upper two stories to remain in place, saving time and


money, as well as removing some risk. The brainstorming about risks needs to


include looking for opportunities that could positively impact the project time


for completion.


It seems obvious that failure to plan for the myriad of risks that often affect


project


performance


will


render


the


planning


less


accurate.


Without


risk


management, every item that might appear on a risk register (a checklist of


potential


risks)


is


a


surprise


to


the


project


team


should


it


happen,


diverting


attention and emphasis from the project management and consuming valuable


resources. Most disputes arise from risks that likely were not considered at the


inception


of


the


project


and


might


have


been


eliminated


or


mitigated


with


good risk planning.



.


.


10


计 划风险管理中英文对照外文翻译文献



Once


a


company


develops


a


regular


risk


management


culture,


the


risk


register generates many of the same risks on project after project. However, a


company’s ‘‘risk



register’’ should not be a fixed template, used as is on all its


projects. The list must be updated and customized for each project taking into


consideration its own risks. These lessons learned, when incorporated into the


project schedule through the risk management


program,


are


invaluable


in


helping


to


minimize


threats


that


carry


negative


impacts


and


take


advantage


of


opportunities


that


bring


positive


impacts


to


project comp.



IMPORTANCE OF GOOD PLANNING FOR RISK MANAGEMENT




The quality of the risk management plan will control the usefulness of the


risk


analysis.


This


quality


is


achieved


through


developing


a


good


and


encompassing


master


risk


register


in


a


brainstorming


workshop


with


experienced


attendees,


and


following


that


process


with


analysis


and


risk


allocation.


This


is


combined


with


a


process


of


continuing


risk


monitoring


during updates as well as continuous cycles of risk management.


Participants


in


the


workshop


will


often


comment


that


they


cannot


take


certain risks into account because they do not have control of the risks or they


have


no


idea


if


that


risk


will


actually


happen.


One


of


the


typical


issues


is


repeated


cycles


of


shop


drawings,


where


experience


tells


us


that


a


complicated design may cause structural steel shop drawings to be rejected,


requiring


revision


and


resubmission.


Some


stakeholders


feel


that


this


is



.


.


11


计划风险管理中英文对照外文翻译文献

< br>


beyond


their


ability


to


plan


for


and


therefore,


the


schedule


should


ignore


it


and assume the risk will not happen. Accepting this assumption minimizes the


risk identification and analysis process. This type of risk should be identified,


and then during the qualitative analysis, it will be weeded out as a low priority


or incorporated as a high priority. However, if the risk is just not included on


the risk register, the opportunity to analyze it is lost.


With a thorough and organized risk workshop, based on a good master risk


register,


and


participation


by


the


major


stakeholders


as


well


as


the


project


management


team,


the


output


of


the


risk


analysis


will


be


very


useful.


The


most likely risks will be identified and analyzed, and with the rest of the risk


management


steps,


the


schedule


will


evolve


into


a


risk-adjusted


schedule,


capable of reasonable analysis and realistic completion predictions.


RISK SHIFTING IN CONTRACTS




Contract language may have a significant impact on how much of the risk


each


party


carries.


Sometimes


called


exculpatory


clauses,


this


language


attempts to shift or apportion undetermined risk. Contracts are often used to


control


or


assign


risk


to various


parties, or


just to


assign it


to


a


party


other


than


the


owner.


Many


owners,


developers,


and


contractors


prefer


using


standard contract forms, such as those specially developed by organizations


such


as


the


American


Institute


of


Architecture


(AIA),


the


Construction


Management Association of America (CMAA), and the


Associated


General


Contractors


(AGC)


in


the


United


States


and


FIDIC


or



.


.


12

-


-


-


-


-


-


-


-



本文更新与2021-02-11 21:04,由作者提供,不代表本网站立场,转载请注明出处:https://www.bjmy2z.cn/gaokao/638945.html

计划风险管理中英文对照外文翻译文献的相关文章

  • 爱心与尊严的高中作文题库

    1.关于爱心和尊严的作文八百字 我们不必怀疑富翁的捐助,毕竟普施爱心,善莫大焉,它是一 种美;我们也不必指责苛求受捐者的冷漠的拒绝,因为人总是有尊 严的,这也是一种美。

    小学作文
  • 爱心与尊严高中作文题库

    1.关于爱心和尊严的作文八百字 我们不必怀疑富翁的捐助,毕竟普施爱心,善莫大焉,它是一 种美;我们也不必指责苛求受捐者的冷漠的拒绝,因为人总是有尊 严的,这也是一种美。

    小学作文
  • 爱心与尊重的作文题库

    1.作文关爱与尊重议论文 如果说没有爱就没有教育的话,那么离开了尊重同样也谈不上教育。 因为每一位孩子都渴望得到他人的尊重,尤其是教师的尊重。可是在现实生活中,不时会有

    小学作文
  • 爱心责任100字作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文
  • 爱心责任心的作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文
  • 爱心责任作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文