1




为什么资格预审?



why prequalification




The successful execution of contracts for large buildings, civil engineering, supply


and installation, turnkey, and design- and-build projects requires that contracts are


awarded only to firms, or combinations of firms, that are suitably experienced in the


type


of


work


and


construction


technology


involved,


that


are


financially


and


managerially


sound,


and


that


can


provide


all


the


equipment


required


in


a


timely


manner.


The


assessment


by


an


implementing


agency


of


the


suitability


of


firms


to


carry


out


a


particular


contract


prior


to being invited to submit a bid is a process called


prequalification.


2.

< br>资格预审会不会降低后续施工招标中的积极性




不会。投标时并不是越多越好,而是要选择合格的承包商。不合格的承包商没有可比性。同一 流


的建筑公司,管理成本正规


i


,报价 保证自己的利润。竞争的是技术实力,投入更多精力来编织技术


标,竞争力更强。



同一档次的不是越多越好,二流三流成本低管理不好,容易胡报价。



t of prequalification


The


prequalification


process


is


of


benefit


to


both


bidders


and


Executing


Agencies


alike,


in that


?


the process enables prospective bidders, who may be insufficiently qualified on


their


own,


to


avoid


the


expense


of


bidding,


or


to


form


a


joint


venture


that


may


give


a


better


chance


of


success;


?


with


prequalification,


well


qualified


firms


will


price


their


bids


with


the knowledge that they are competing against other qualified bidders meeting realistic


minimum


competence


criteria,


and


with


the


assurance


that


inadequately


qualified


competitors


will be excluded from submitting unrealistically low bids, leading contractors are


encouraged


to


bid;


?


prequalification


enables


Executing


Agencies


to


assess


the


interest


from


qualified firms generated by the contract and, in the event that only a limited number of


applications are received, to make any necessary adjustments in the procurement process;


?


it helps to expose potential conflicts of interest of an applicant with other parties


involved


in


this


prequalification


process;


?


it


reduces


the


amount


of


work


and


time


involved


by


Executing


Agencies


in


evaluating


bids


from


unqualified


contractors;


it


encourages


local


firms to form joint ventures with other local or international firms, thereby benefiting


from their resources and experience;


?


it enables the Executing Agencies to assess the


likelihood


o


f


contractors’


eligibility


for


domestic



bidder


price


preference


in


borrowing


countries where this is applicable; and


?


it reduces significantly, if not eliminates,


problems of rejection associated with low-priced bids submitted by bidders of doubtful


capability.


e contract



将标划分成很多块来判断承保能力。不同性质的标段由不同 的承包商承担。判断承保能力。



5.


资格预审包含的内容



Instructions to Applicants (ITA). Application Data Sheet. Qualification Criteria.


Application Forms. Eligible Countries. Scope of Contract.


6.


业主有权拒绝资格预审资料



18.1 The Employer reserves the right to accept or reject late Applications.


s in qualification


Any change in the qualification status of an Applicant after being prequalified in


accordance with ITA Clause 27 shall be subject to the written approval of the Employer.


Any


such


change


shall


be


submitted


to


the


Employer


not


later


than


fourteen


(14)


days


after


the date of the Invitation to Bid. Such approval shall be denied if as a consequence of


any


change,


(a)


the


prequalified


Applicant,


after


the


change,


no


longer


substantially


meets


the qualification criteria set forth in Section III, Qualification Criteria; or (b) a new


partner that had not been prequalified as an Applicant or a Specialist Subcontractor as


per ITA 24.2 is added to a prequalified Applicant.


8.


甲方组织招标编制的招标文件的内 容



PART I Bidding Procedures



Section 1 - Instructions to Bidders (ITB)



Section 2


- Bid Data Sheet (BDS)



Section 3 - Evaluation and Qualification Criteria (EQC)



Section 4 - Bidding Forms (BDF)



Section 5 - Eligible Countries (ELC)



PART II


Req uirements



Section 6 - Employer



s Requirements (ERQ)



PART III Conditions of


Contract and Contract Forms



Section 7 - General Conditions (GCC)


Section 8 - Particular Conditions (PCC)



Section 9 - Contract Forms (COF)


10.


招标文件的修改



8.1 At any time prior to the deadline for submission of bids, the Employer may amend the


Bidding Document by issuing addenda. 8.2 Any addendum issued shall be part of the Bidding


Document


and


shall


be


communicated


in


writing


to


all


who


have


obtained


the


Bidding


Document


from the Employer in accordance with ITB 6.3.


11.


投标文件的内容



The Bid shall comprise the following:(a) Letter of Bid; (b) completed schedules as


required, including priced Bill of Quantities, in accordance with ITB 12 and 14; (c) Bid


Security, in accordance with ITB 19; (d) alternative bids, if permissible, in accordance


with ITB 13; (e) written confirmation authorizing the signatory of the Bid to commit the


Bidder, in accordance with ITB 20.2; (f) documentary evidence in accordance with ITB 17


establishing the


Bidder



s qualifications to perform the contract if its Bid is accepted;


(g) Technical Proposal in accordance with ITB 16; (h) any other document required in the


BDS.


12. alternative bids


13.1


Unless


otherwise


indicated


in


the


BDS,


alternative


bids


shall


not


be


considered.13.2


When alternative times for completion are explicitly invited, a statement to that effect


will


be


included


in


the


BDS,


as


will


the


method


of


evaluating


different


times


for


completion.


13.3 Except as provided under ITB 13.4 below, Bidders wishing to offer technical


alternatives to the requirements of the Bidding Document must first price the Employer



s design as described in the Bidding Document and shall further provide all information


necessary


for


a


complete


evaluation


of


the


alternative


by


the


Employer,


including


drawings,


design calculations, technical specifications, breakdown of prices, and proposed


construction methodology and other relevant details. Only the technical alternatives, if


any, of the lowest evaluated Bidder conforming to the basic technical requirements shall


be considered by the Employer. 13.4 When specified in the BDS, Bidders are permitted to


submit alternative technical solutions for specified parts of the Works. Such parts will


be


identified


in


the


BDS


and


described


in


Section


6


(Employer



s


Requirements).


The


method


for their evaluation will be stipulated in Section 3 (Evaluation and Qualification


Criteria).


13.


开标顺序:


First, envelopes marked



WITHDRAWAL



shall be opened and read out


and the envelope with the corresponding bid shall not be opened, but returned to


the Bidder. Next, envelopes marked



SUBSTITUTION

< br>”


shall


be


opened


and


read


out


and


exchanged


with


the


corresponding


bid being


substituted,


and


the


substituted


bid


shall


not


be


opened,


but


returned


to


the


Bidder.


Envelopes


marked



MODIFICAT ION



shall


be


opened


and


read


out


with


the


corresponding


bid. All other envelopes shall be opened one at a time



如何判断标书是符合还是不符合包括哪几个内容




1.


未按业主要求投标,


2


增大业主责任,减轻自己责任


3


,关 键资料未提交



ions,reservations and omissions


(a)



D eviation



is


a


departure


from


the


requirem


ents


specified


in


the


Bidding


Document;


(b)



Reservation< /p>



is the setting of limiting conditions or withholding from complete


acceptance


of


the


requirements


specified


in


the


Bidding


Document;


and


(c)



Omission



is


the


failure


to


submit


part


or


all


of


the


information


or


documentation


required


in


the


Bidding


Document.


15.


实质性不符合



符合:


A


substantially responsive


bid is one that meets the requirements of the Bidding


Document without material deviation, reservation, or omission. A material deviation,


reservation,


or


omission


is


one


that,


(a)


if


accepted,


would:(i)


affect


in


any


substantial


way


the


scope,


quality,


or


performance


of


the


Works


specified


in


the


Contract;


or


(ii)


limit


in any substantial way,


inconsistent with the Bidding Document, the Employer



s rights or


the


Bidder



s


obligations


under


the


proposed


Contract;


or


(b)


if


rectified,


would


unfairly


affect


the


competitive


position


of


other


Bidders


presenting


substantially


responsive


bids.


16.


非实质性不符合可以补救,实质性不能补救


Provided that


a bid is substantially


responsive, the Employer may waive any nonconformities in the bid that do not


constitute a material deviation, reservation or omission.


Provided that


a bid


is substantially responsive, the Employer may request that the Bidder submit the


necessary information or documentation, within a reasonable period of time, to


rectify nonmaterial nonconformities in the bid related to documentation


requirements.


Provided


that


a


bid


is


substantially


responsive,


the


Employer


shall


rectify nonmaterial nonconformities related to the Bid Price.

< br>17.


投标人资格审查程序



Q ualification of the Bidder


):


36.1



The Employer shall


determine to its satisfaction whether the Bidder that is selected as having


submitted the lowest evaluated and substantially responsive bid meets the


qualifying criteria specified in Section 3 (Evaluation and Qualification


Criteria).


36.2



The determination shall be based upon an examination of the


documentary evidence of the Bidder



s qualifications submitted by the Bidder,


pursuant


to


ITB


17.1.


36.3


An


affirmative


determination


shall


be


a


prerequisite


for


award of the Contract to the Bidder. A negative determination shall result in


disqualification


of


the


bid,


in


which


event


the


Employer


shall


proceed


to


the


next


lowest


evaluated


bid


to


make


a


similar


determination


of


that


Bidder



s


qualifications


to perform satisfactorily.


18.


业主评标的依据:


(a)


the


bid


price,


excluding


Provisional


Sums


and


the


provision,

-


-


-


-


-


-


-


-



本文更新与2021-02-11 08:23,由作者提供,不代表本网站立场,转载请注明出处:https://www.bjmy2z.cn/gaokao/635125.html