关键词不能为空

当前您在: 主页 > 英语 >

Sample Letters for Contractor under Orange Book of FIDIC(dra

作者:高考题库网
来源:https://www.bjmy2z.cn/gaokao
2021-02-13 14:45
tags:

-

2021年2月13日发(作者:蕴含)


No.



1


2


3


4


5


6


7


8


9


10


11


12


13


14


15


16


17


18


19


20


21


22


23



Chart No.



3


3; 4


3


3


3


3; 9


10


10


13


13



11


11


11


11


11



14


14


14


14


14


15



Draft Letters


For


FIDIC Design, Build and Turnkey



Clause


Subject




4.5


Proposal for use of Sub-contractor


4.11


Unforeseen Conditions


4.16


Removal of equipment


4.24


Fossil, coins, etc.



discovery


4.24


Fossil, coins, etc



delay and disruption


8.3


Instruction to apply for Extension of Time


8.8


Consequence of Suspension



8.10


Prolonged Suspension (Over 84 days)


10.1


Apply for Taking-Over Certificate


10.1


Taking-Over Certificate where works in use


10.2(b)


Interim Application for Payment


13.3


Specimen Application (4 pages)


13.10


Statement at Completion


13.11


Draft Final Statement


13.11


Final Statement


13.12


Discharge


13.16


Change in Legislation


Delayed payment



suspend work/Reduce rate


16.1


16.1


Delayed payment



extra time and costs


16.2


Employer’s Default –


Notice of Termination


19.3


Notice of Force Majeure


19.6


Force Majeure



Notice of termination


20.1


Notice of Intention to Claim extra payment





Draft No.1


Clause 4.5



Subcontract


To Employer’s Representative




….(Item of Works)…




As required by Clause 4.5 of the Conditions of Contract we would advise you that we propose


to


employ …(name of


sub-


contractor)… to


execute … (item of work)… and hereby request


your consent to this appointment.



Subject


to


such consent,


we would notify


you that the sub-contracted works will commence


on …(date –



not less than 28 days of tar this letter)…




Yours faithfully




Draft No.2


Clause 4.11



Unforeseen Conditions


To Employer’s Representative




….(Title)…




We have to advise that during the course of the Works we have encountered …(description of


conditions)… on …(date)…




These conditions were not foreseeable and we therefore hereby give notice thereof as required


by Clause 4.11 of the Conditions of Contract.



The effect of these conditions will be delay the Works and cause us to incur additional costs we


therefore give you notice of our intention to seek an extension of time and additional payment


pursuant to Clause 8.3 and 20.1 of the Conditions of Contract.



Yours faithfully



Draft No.3


Clause 4.16



Removal of Equipment


To Employer’s Representative




Removal of ….(Item of Equipment)…




We


propose


to


remove



(item


of


equipment)…


from


the


Site


on


…(date)…


following


completion of … (work upon which equipment was engaged)…




As required by Clause 4.16 of the Conditions of Contract we would be pleased to receive your


consent to this action.



Yours faithfully




Draft No.4


Clause 4.24



Fossils, coins, etc.


To Employer’s Representative




…(Part of the Works)…




During


…(activity)…


in


…(location


or


part


of


Works)



on


(date)…


we


discovered



(article)…




Unless


instructed to


the


contrary we shall


dispose of …(article)… by …(propo


sed means


of


disposal) …on (date for disposal)…





Yours faithfully




Draft No.5


Clause 4.24



Fossils, coins, etc.


Delay & Disruption


To Employer’s Representative




…(Part of the Works)…




Following


discovery


of


…(article)…


and


your


instructions


dated



(date)



in


connection


therewith we incurred a delay to the progress of the Works and additional costs.



In accordance with the provisions of Clause 4.24 of the Conditions of Contract we hereby give


notice of our intention to seek an extension of time and additional payment pursuant to Clause


8.3 and 20.1 respectively.



Yours faithfully


Draft No.6


Clause 8.3



Intent to Claim EOT


To Employer’s Representative




Extension of Time



We hereby give notice of an intention to apply for an Extension of Time on account of


…(brief


description of event)…




This notice is given under the provisions of Clause 8.3 of the Conditions of Contract.



We shall maintain contemporary records and submit full supporting details of our application


as required thereby.




Yours faithfully




Draft No.7


Clause 8.8



Consequence of Suspension


To Employer’s Representative




cc



Employer



Suspension of … (as described in Employer’s Representative’s instruction)…




We hereby give notice pursuant to Clause 8.8 of the Conditions of Contract that on account of


following instructions given by the Employer’s Representative in respect of the above we have


suffered delay and/or incurred Cost. Therefore we give you notice that we intend to apply for


an


extension


of


time


and


seek


additional


payment


pursuant


to


Clause


8.3


and


20.1


of


the


Conditions of Contract.




Yours faithfully



Draft No.8


Clause 8.10



Prolonged Suspension


To Employer’s Representative




Suspension of … (as described in original instruction)…




The above suspension having continued for more than 84 days we hereby give notice pursuant


to Clause 8.0 of the Conditions of Contract requiring permission to proceed within 28 days.



If permission is not granted within that period we shall ...(treat the suspension as an omission


under Clause 14/Terminate o


ur employment under Clause 16.2)*…




Yours faithfully



* as appropriate




Draft No.9


Clause 10.1


Taking Over Certificate


To Employer’s Representative




… (Section …/The Works)*


--- Taking Over Certificate



We are of the opinion that … (Section…/The Works)*…


will be complete and ready for taking


over on …(date)…




Accordingly, ad provided for by Clause 10.1 of the Conditions of Contract we hereby apply for


a Taking Over Certificate for … (that Section/The Works)…





Yours faithfully



* delete as appropriate.




Draft No.10


Clause 10.1


Taking Over Certificate


Re-application


To Employer’s Representative




… (Section …/The Works)*


--- Taking Over Certificate



We advise that we have completed the work specified to be required to enable you to issue a


Taking



Over Cert


ificate for …(Section…/the Works)* … as detailed in … (letter minutes of


meeting, etc.)…




Accordingly, as provided for by Clause 10.1 of the Conditions of Contract we hereby re- apply


for a Taking-


Over Certificate for … (that Section/The Works)…





Yours faithfully



* delete as appropriate.




Draft No.11


Clause 10.2(b)


Taking Over Certificate



To Employer’s Representative




… (the part)


--- Taking Over Certificate



Pursuant


to


Clause


10.2


(b)


of


the


Conditions


of


Contract


we


request


that


you


issue


a


Taking- Ove


r


Certificate


for



(the


part


of


the


Works)…


which


the


Employer


look


into


use


on …(date)…





Yours faithfully




Draft No.12


Clause 13.3


Interim Payment Application



To Employer’s Representative




Application for Interim Payment No. …




Pursuant to


Clause 13.3


of the Conditions of Contract


we are pleased to


enclose … (No.)…


copies


of


our


statement


showing


the


amounts


to


which


we


are


now


entitled


together


with


supporting documents.



The detailed report on progress required by Clause 4.15 of the Conditions of Contract has been


submitted under separate cover.



We look forward to receipt of a copy of your Interim Payment Certificate.



Yours faithfully




Application for Interim Payment No. ….





















Period ……





a)



Estimated Contract Value from Page No.2


Tk. ………….



b)



Changes in Legislation





…………







Sub-total



Contract Price





…………



c)



Deduct Retention @ 10% of Contract Price





…………



(Maximum: 5% of Contract Price, Tk. 70,826,515)






Sub-total






…………



d)



Plant and Materials for Permanent Works (80% of cost)





…………



e)



Claims





…………







Sub-total





…………



f)




Advance Payment

















Tk. ………








Deduct repayment




25% of a, b, d, &e



………..






…………







Sub



total






…………



g)




Deduct Amounts Previously Certified





…………








Amount Now Due





………..





Signed …………….



Date ………..






.Page 1.


Application for Interim Payment No. …



Period …





Estimated Contract Value



Section



Contract Price



% Complete



1.



Section 1 of the Works






Completion & approval of design




………….





………..





Embankment Protection




………….





………..





Filling




………….





………..





Dredging




………….





………..





Total of Section 1




2. Section 2 of the Works




………….





………..



3. Section 3 of the Works






Dredging




………….





………..





Embankment Protection




………….





………..





Filling




………….





………..





Fencing




………….





………..





Total of Section 3




………….





………..





Total for the Works




………….





………..





Add Variation as Schedule Page 3









Total carried to Page 1








.Page 2.



Price to date



………….



………….



………….



………….




………….




………….



………….



………….



………….



………….



………….



…………





-


-


-


-


-


-


-


-



本文更新与2021-02-13 14:45,由作者提供,不代表本网站立场,转载请注明出处:https://www.bjmy2z.cn/gaokao/650761.html

Sample Letters for Contractor under Orange Book of FIDIC(dra的相关文章

  • 余华爱情经典语录,余华爱情句子

    余华的经典语录——余华《第七天》40、我不怕死,一点都不怕,只怕再也不能看见你——余华《第七天》4可是我再也没遇到一个像福贵这样令我难忘的人了,对自己的经历如此清楚,

    语文
  • 心情低落的图片压抑,心情低落的图片发朋友圈

    心情压抑的图片(心太累没人理解的说说带图片)1、有时候很想找个人倾诉一下,却又不知从何说起,最终是什么也不说,只想快点睡过去,告诉自己,明天就好了。有时候,突然会觉得

    语文
  • 经典古训100句图片大全,古训名言警句

    古代经典励志名言100句译:好的药物味苦但对治病有利;忠言劝诫的话听起来不顺耳却对人的行为有利。3良言一句三冬暖,恶语伤人六月寒。喷泉的高度不会超过它的源头;一个人的事

    语文
  • 关于青春奋斗的名人名言鲁迅,关于青年奋斗的名言鲁迅

    鲁迅名言名句大全励志1、世上本没有路,走的人多了自然便成了路。下面是我整理的鲁迅先生的名言名句大全,希望对你有所帮助!当生存时,还是将遭践踏,将遭删刈,直至于死亡而

    语文
  • 三国群英单机版手游礼包码,三国群英手机单机版攻略

    三国群英传7五神兽洞有什么用那是多一个武将技能。青龙飞升召唤出东方的守护兽,神兽之一的青龙。玄武怒流召唤出北方的守护兽,神兽之一的玄武。白虎傲啸召唤出西方的守护兽,

    语文
  • 不收费的情感挽回专家电话,情感挽回免费咨询

    免费的情感挽回机构(揭秘情感挽回机构骗局)1、牛牛(化名)向上海市公安局金山分局报案,称自己为了挽回与女友的感情,被一家名为“实花教育咨询”的情感咨询机构诈骗4万余元。

    语文