Tendering
投标
Contractor pre-
qualification
承包商资格预审
Prepare list of contractors
for pre-
qualification
准备资格预审的承包商目录
Prepare pre-qualification
document for
contractors
准备承包商的预审文件
Issue pre-qualification
document to P&G for review
为评审向
P
&
G
发行预审文件
Update pre-
qualification doc
更新预审文件
Issue prequalification doc
to contractors
向承包商发行预审文件
Pre -qualification
period
预审期
Pre -qualification
return
预审返回
Pre -qualification assessment and
shortlist prepare
预审评估和候选人预备
Issue shortlist of
contractors for tender to P&G
向
P
&
G
发行投标的承包商候选人<
/p>
P&G review and
confirm shortlistP
&
G
< br>评估和确认候选人
P&G
confirmation of shortlist for tenderP
&<
/p>
G
关于投标候选人的确认
Mail works
tender
邮件作品投标
Preparation of boQ,tender documents
boQ
,投标文件准备
Issue to P&G for review
为评估向
P
&
G
发行<
/p>
P&G review & com
mentP
&
G
评估及评论
Issue tender doc
comments
发行投标文件评论
Update tender
documents
更新投标文件
Issue tender
发布投标
Tender period
投标期
Tender return
投标返回
Issue tender addenda
发行投标附录
Return of tender addenda
投标附录返回
Tender evaluation & award
投标评估及决标
Tender assessment & evaluation
投标估价及评估
Contractor interviews
承包商会面
Tender clarifications
投标说明
Tender negotiations
投标谈判
Prepare tender recommendation report
准备投标推为报告
Issue tender recommendation report
发行投标推为报告
Confirmation of appointment by P&G P
&
G
任命确认
Letter of award
决标信
估
算
/
费用估算:
estimate/c
ost estimate;
估算类型:
types of estimate;
详细估算:是偏差幅度最小的估算,
defined
estimate;
设备估算:
equipment estimate;
分析估算:
analysis
estimate;
报价估算
:proposal estimate;
控制估算:
control
estimate;
初期控制估算:
interim control
estimate/initial control estimate
批准的控制估算:
initial approved
cost
核定估算:
check
estimate
首次核定估算:
first check estimate
二次核定估算:
production check
estimate
人工时估算:
man hour estimate
材料费用
/
直接材料费用:
material cost/direct material
cost
设备费用
/
设备购买费用:
equipment cost/purchased
cost of equipment
散装材料费用
/
散装材料购买费用:
bulk
material cost/purchased cost of bulk material
施工费用:
construction cost
施工人工费用:
labor
cost/construction force cost
设备安装人工费用:
labor cost
associated with equipment
散装材料施工安装人工费用:
labor cost
associated with bulk materials
人工时估算定额:
standard manhours
施工人工时估算定额:
standard labor
manhours
标准工时定额:
standard hours
劳动生产率:
labor
productivity/productivity factor/productivity
ratio
修正的人工时估算值:
adjusted manhours
人工时单价:
manhours
rate
施工监督费用:
cost
of construction supervision
施工间接费用:
cost of contruction
indirects
分包合同费用
/
现场施工分包合同费用:
subcontract
cost/field subcontract cost
公司本部费用:
home office cost
公司管理费用:
overhead
非工资费用:
non
payroll
开车服务费用:
cost of start-up
services
其他费用:
other cost
利润
/
预期利润:
profit/expected profit
服务酬金:
service gains
风险:
risk
风险分析:
risk
analysis
风险备忘录:
risk memorandum
未可预见费:
contingency
基本未可预见费:
average
contingency
最大风险未可预见费:
maximum risk
contingency
用户变更
/
合同变更:
cilent change/contract
change
认可的用户变更:
approved client
change
待定的用户变更:
pending client
change
项目变更:
project change
内部变更:
internalchange
批准的变更:
authoried
change
强制性变更:
mandatory change
选择性变更:
optional
change
内部费用转换:
internal transfer
认可的预计费用:
anticipated approved
cost
涨价值:
escalation
项目费用汇总报告:
project cost
summary report
项目实施费用状态报告:
project operation
cost status report
总价合同:
lump sum contract
偿付合同:
reimbursible contract
预算:
budget
-
-
-
-
-
-
-
-
-