-
中英文对照外文翻译
(
文档含英文原文和中文翻译
)
Deep Excavations
ABSTRACT
:
All
major
topics
in
the
design
of
in-situ
retaining
systems for deep
excavations in urban areas are outlined. Type of
wall, water
related problems and water
pressures, lateral earth pressures, type of
support,
solution
to
earth
retaining
walls,
types
of
failure,
internal
and
external
stability problems.
KEYWORDS
: deep excavation;
retaining wall; earth pressure;
INTRODUCTION
Numbers
of
deep
excavation
pits
in
city
centers
are
increasing
every
year. Buildings,
streets surrounding excavation locations and
design of very
deep basements make
excavations formidable projects. This chapter has
been
organized in such a way that
subjects related to deep excavation projects are
summarized in several sections in the
order of design routine. These are types
of in-situ walls, water pressures and
water related problems. Earth pressures
in cohesionless and cohesive soils are
presented in two different categories.
Ground
anchors,
struts
and
nails
as
supporting
elements
are
explained.
Anchors are given
more emphasis compared to others due to widespread
use
observed in the recent
years. Stability of retaining systems
are discussed as
internal
and
external
stability.
Solution
of
walls
for
shears,
moments,
displacements
and
support
reactions
under
earth
and
water
pressures
are
obtained making use of
different methods of analysis. A pile wall
supported
by anchors is solved by three
methods and the results are compared. Type of
wall
failures,
observed
wall
movements
and
instrumentation
of
deep
excavation projects are
summarized.
1. TYPES OF
EARTH RETAINING WALLS
1.1
Introduction
More than several types of in-situ
walls are used to support excavations.
The criteria for the selection of type
of wall are size of excavation, ground
conditions,
groundwater
level,
vertical
and
horizontal
displacements
of
adjacent
ground
and
limitations
of
various
structures,
availability
of
construction, cost, speed
of work and others. One of the main decisions is
the
water-tightness
of
wall.
The
following
types
of
in-situ
walls
will
be
summarized below;
1. Braced walls, soldier
pile and lagging walls
2.
Sheet-piling or sheet pile walls
3. Pile walls (contiguous, secant)
4. Diaphragm walls or
slurry trench walls
5.
Reinforced concrete (cast-in-situ or
prefabricated) retaining walls
6. Soil nail walls
7. Cofferdams
8.
Jet-grout and deep mixed walls
9. Top-down construction
10. Partial excavation or island method
1.1.1 Braced Walls
Excavation proceeds step by
step after placement of soldier piles or so
called
king
posts
around
the
excavation
at
about
2
to
3
m
intervals.
These
may be steel H, I or
WF sections. Rail sections and timber are also
used. At
each level horizontal waling
beams and supporting elements (struts, anchors,
nails) are constructed.
Soldier piles are driven or commonly placed in
bored
holes
in
urban
areas,
and
timber
lagging
is
placed
between
soldier
piles
during the excavation. Various details
of placement of lagging are available,
however,
precast
units,
in-situ
concrete
or
shotcrete
may
also
be
used
as
alternative
to
timber.
Depending
on
ground
conditions
no
lagging
may
be
provided in relatively shallow pits.
Historically
braced
walls
are
strut
supported.
They
had
been
used
extensively before the
ground anchor technology was developed in
1970
?
s.
Soils
with some cohesion and without water table are
usually suitable for this
type of
construction or dewatering is
accompanied if required and allowed.
Strut support is commonly preferred in
narrow excavations for pipe laying or
similar
works
but
also
used
in
deep
and
large
excavations
(See
Fig
1.1).
Ground
anchor support is increasingly used and preferred
due to access
for
construction
works
and
machinery.
Waling
beams
may
be
used
or
anchors
may be placed
directly on soldier piles without any beams.
1.1.2 Sheet-piling or Sheet Pile Walls
Sheet pile is a thin steel
section (7-30 mm thick) 400-500 mm wide. It is
manufactured
in
different
lengths
and
shapes
like
U,
Z
and
straight
line
sections (Fig. 1.2). There are
interlocking watertight grooves at the sides, and
they
are
driven
into
soil
by
hammering
or
vibrating.
Their
use
is
often
restricted
in
urbanized
areas
due
to
environmental
problems
like
noise
and
vibrations.
New
generation
hammers
generate
minimum
vibration
and
disturbance,
and
static
pushing
of
sections
have
been
recently
possible.
In
soft
ground several sections may be driven using a
template. The end product
is a
watertight steel wall in soil. One side (inner) of
wall is excavated step by
step
and
support
is
given
by
struts
or
anchor.
Waling
beams
(walers)
are
frequently used. They
are usually constructed in water bearing soils.
Steel
sheet
piles
are
the
most
common
but
sometimes
reinforced
concrete
precast
sheet
pile
sections
are
preferred
in
soft
soils
if
driving
difficulties
are
not
expected.
Steel
piles
may
also
encounter
driving
difficulties in very
dense, stiff soils or in soils with boulders.
Jetting may be
accompanied during the
process to ease penetration. Steel sheet pile
sections
used in such difficult driving
conditions are selected according to the driving
resistance rather than the design
moments in the project. Another frequently
faced
problem
is
the
flaws
in
interlocking
during
driving
which
result
in
leakages
under
water
table.
Sheet
pile
walls
are
commonly
used
for
temporary
purposes
but
permanent
cases
are
also
abundant.
In
temporary
works sections are
extracted after their service is
over,
and they
are reused
after
maintenance.
This
process
may
not
be
suitable
in
dense
urban
environment.
1.1.3 Pile
Walls
In-situ pile
retaining walls are very popular due to their
availability and
practicability. There
are different types of pile walls (Fig. 1.3). In
contiguous
(intermittent)
bored
pile
construction,
spacing
between
the
piles
is
greater
than the diameter of piles. Spacing is
decided based on type of soil and level
of design moments but it should not be
too large, otherwise pieces of lumps
etc.
drop
and
extra
precautions
are
needed.
Cohesive
soils
or
soils
having
some
cohesion
are
suitable.
No
water
table
should
be
present.
Acceptable
amount of water is collected at the
base and pumped out. Common diameters
are 0.60, 0.80, 1.00 m. Waling beams
(usually called ?breasting
beams
?
) are
Tangent
piles
with
grouting
in
between
are
used
when
secant
piling
or
diaphragm
walling
equipment
is
not
available
(i.e.
in
cases
where
ground
water exists). Poor
workmanship creates significant problems.
Secant bored
pile walls are formed by keeping spacing of piles
less than
diameter
(S
It
is
a
watertight
wall
and
may
be
more
economical
compared
to
diaphragm
wall
in
small
to
medium
scale
excavations
due
to
cost of
site operations and bentonite plant.
There
is
also
need
for
place
for
the
plant.
It
may
be
constructed
“hard
-
hard” as
well as “soft
-
hard”. “Soft”
concrete pile
contains low cement
content and some bentonite. Primary
unreinforced piles are constructed first
and then reinforced secondary piles are
formed by cutting the primary piles.
Pile construction methods may vary in
different countries for all type of pile
walls
like
full
casing
support,
bentonite
support,
continuous
flight
auger
(CFA) etc. mostly
reinforced concrete but sheet pile sections or
steel beams
are also used.
1.1.4 Diaphragm Walls
Diaphragm wall provides
structural support and water tightness. It is a
classical technique for many deep
excavation projects, large civil engineering
works,
underground
car
parks,
metro
pits
etc.
especially
under
water
table.
These reinforced concrete diaphragm
(continuous) walls are also called slurry
trench walls due to the reference given
to the construction technique where
excavation of wall is made possible by
filling and keeping the wall cavity full
with
bentonite-water
mixture
during
excavation
to
prevent
collapse
of
the
excavated
vertical surfaces. Wall thickness varies between
0.50 m and 1.50 m.
The wall is
constructed panel by panel in full lengths are 2
m to
10 m. Short lengths (2-2.5 m) are
selected in unstable soils or under very high
surcharges.
Nowadays
depth
of
panels
water
stops
exceeded
100
m,
excavation
depths
exceeded
50
m.
Different
panel
shapes
other
than
the
conventional straight
section like T, L, H, Y
, + are possible
to form and used
for
special
purposes.
Panel
excavation
is
made
by
cable
or
kelly
supported
buckets
and by a recent
design
called ?cutter
?
or ?hydrofraise
?
which is a
pair of
hydraulically operated rotating disks provided
with hard cutting tools.
Excavation
in
rock
is
possible.
Slurry
wall
technique
is
a
specialized
technique
and
apart
from
the
bucket
or
the
frame
carrying
the
cutter
equipment
like
crawler
crane,
pumps,
tanks,
desanding
equipment,
air
lifts,
screens,
cyclones,
silos,
mixers,
extractor
are
needed.
Tremie
concrete
is
placed
in
the
slurry
starting
from
the
bottom
after
lowering
reinforcement
cages. Joint between the panels is a
significant detail in water bearing soils
and steel pipe, H-beam or water stops
are used.
1.1.5
Reinforced Concrete Retaining Walls Excavation in
Stages
It
is
a
common
type
of
staged
excavation
wall
usually
supported
by
ground anchors. Soils
with some cohesion are suitable because each stage
is
first excavated before formwork and
concrete placement. No water table or
appreciable amount of water should be
present. Sometimes micropile support
is
given if required due to expected cave-ins.
1.1.6 Soil Nail
Walls
Similar to the method
above excavation is made step by step (1.5 to 2 m
high). Shotcrete is common for facing
and wiremesh is used. Soft facing is
also
possible
making
use
of
geotextiles.
Hole
is
drilled,
ordinary
steel
bars
are
lowered,
and
grout
is
placed
without
any
pressure.
Soil
should
be
somewhat
cohesive
and
no
water
table
or
significant
water
flow
should
be
present.
1.1.7
Cofferdams
Cofferdam
is
a
temporary
earth
retaining
structure
to
be
able
to
make
excavation for construction activities.
It is usually preferred in the coastal and
sea environment like bridge piers and
abutments in rivers, lakes etc., wharves,
quay
walls,
docks,
break
waters
and
other
structures
for
shore
protection,
large waterfront structures such as
pump houses, subjected to heavy vertical
and horizontal loads. Sheet piling is
commonly used in various forms other
than
conventional
walls
like
circular
cellular
bodies
or
double
walls
connected
inside
and
filled
with
sand.
Stability
is
maintained
by
sheeting
driven
deeper
than
base,
sand
body
between
sheeting
and
inside
tie
rods.
Earth embankments and concrete bodies
are also used. Contiguous, tangent,
secant
piles
or
diaphragm
walls
are
constructed
in
circular
shapes,
and
no
internal
bracing
or
anchoring
is
used
to
form
a
cofferdam.
Reinforced
concrete
waling
beams
support
by
arching.
Shafts
are
also
made
with
this
method.
Large excavations or
project details may require additional lateral
support.
1.1.8
Jet Grout and Deep Mixed Walls
Retaining walls are made by single to
triple row of jet grout columns or
deep
mixed columns. There is a soil mixed wall(SMW)
technique specially
developed for wall
construction where H sections are used for
reinforcement.
Single
reinforcing
bar
is
placed
in
the
central
hole
opened
for
jet
grout
columns. Anchors,
nails or struts may be used for support.
1.1.9 Top Down Construction
Retaining
structure
(generally
diaphragm
wall)
is
designed
and
constructed
as
permanent
load
bearing
walls
of
basement.
Piles
or
barettes
are
similarly placed to complete the structural frame.
Top slab is cast at the
ground surface
level, and excavation is made under the slab by
smaller sized
excavators and continued
down forming basement slabs at each level. There
are
special
connection
details.
Top
down
method
is
preferred
in
highly
populated
city centers where horizontal and vertical
displacements
are very
critical,
and
anchors
and
struts
are
very
difficult
to
use
due
to
complex
underground facilities and lifeline
structures and site operations are difficult
to perform.
1.1.10 Partial Excavation or Island
Method
It is possible to
give strut support to retaining walls at a later
stage after
constructing central
sections of a building in large size excavations.
Core of
the
structure
is
built
at
the
central
part
making
sloped
excavations
at
peripheral
areas
and
then
the
core
frame
is
used
to
give
support
to
walls
(Figure
1.9).
It
may
be
more
practical
and
construction
time
may
be
less
compared to conventional braced system.
This method may not be suitable in
soft
and weak soils due to stability and deformation
problems during sloped
excavations.
2. EARTH PRESSURES ON IN-
SITU RETAINING WALLS
2.1.
Introduction
Earth pressures on in-situ retaining
walls are rather different than those
on ordinary retaining walls due to the
supporting elements. Free displacement
of
walls
are
not
allowed.
Type
of
support
affects
the
distribution
of
earth
pressure. Strut loads
were measured in strutted excavations in many
countries
in the past, and
recommendations were given. Ground anchor
technology is
relatively
new,
and
data
on
instrumented
anchored
walls
for
total
lateral
pressure
and
for
water
pressure
are
being
accumulated.
Earth
pressure
diagrams
on
strutted
and
anchored
walls
are
expected
to
be
somewhat
different
due
to
stiffer
support
conditions
in
the
former.
Theoretical
approaches will also be discussed.
2.2. Earth
Pressure Distributions on Walls
Terzaghi
and
Peck
(1967)
and
Peck
(1969)
based
on
load
measurements on struts recommend the
pressure distribution shown in Figure
2.1 for cohesionless soils. It is a
uniform pressure and given by Eq. 2.1;
p = 0.65
K
A
γ
t
H
2.1
where K
A
is the
active earth pressure coefficient, H is the height
of wall.
Unit weight (γt) is described
as the bulk unit weight
in the original
references.
Since
braced
excavations
were
generally
dewatered
in
the
past
projects
the
unit
weight
in
the
expression
was
described
as
wet
or
bulk.
If
wall
is
watertight
and
water
table
is
present,
buoyant
unit
weight
should
be
used
under water table and water pressure
should be added.
The rectangular diagram proposed in the
figure is not an actual pressure
distribution
but
an
envelope
obtained
by
plotting
the
measured
strut
loads
converted to
pressure distribution at
each stage
of excavation
including
the
final
depth
covering
all
distributions.
It
is
also
called
apparent
pressure
distribution.
It
is
regarded
as
a
conservative
approach
because
strut
loads
calculated by such an envelope are
generally greater than the measured loads.
Rectang
ular
envelope with
p = 0.2 γt H
is also
recommended by Twine
and Roscoe (1996)
based on more recent field measurements. Similarly
use
of submerged unit weight below
water table and addition of water pressure is
recommended. Data on cohesive soils are
classified for soft to medium stiff
clays and stiff clay.
Anchor or nail supported walls may show
higher lateral displacements,
and
stress
increases
at
the
upper
levels
of
walls
may
be
somewhat
less
compared
to
the
distributions
on
strutted
walls.
However,
there
are
no
documented comparisons. In the solution
of anchored walls by finite element,
boundary
element,
finite
difference
softwares
or
simpler
spring
models
the
analyses may be repeated without
assigning pre-tensions initially like in case
of
nail
supported
walls
and
then
assign
the
calculated
reactions
as
pre-tensions.
There are also recommendations on
selection of the type of distribution
in
relation
to
height
of
braced
walls.
Distributions
based
on
pressure
cell
records
are
recommended
for
all
heights
but
distributions
by
strut
load
measurements are not found suitable for
walls higher than 15 m, they may be
used for walls of 10
–
15 m height depending on
conditions of the ground and
construction and recommended for
heights less than 10 m.
Another common case is an alluvial
profile where clay, silt, sand layers
mixed in different proportions lie in
different thicknesses. If a dominant layer
is
present
one
of
the
above
distributions
may
be
selected,
otherwise
a
theoretical
approach
like
Coulomb’s
earth
pressure
expression
may
be
followed
making
use
of
effective
parameters,
submerged
unit
weights
and
added water pressure.
Effect of different surcharge loads on
walls may be calculated by stress
distributions in elastic medium (e.g.
NA
VFAC 1982). For the upper limit of
very rigid walls the distributions are
doubled. Wide surcharge loads may also
be converted to equivalent heights of
soil layer.
3. SUPPORTING
ELEMENTS
3.1 Ground Anchors
3.1.1 Introduction
Ground
anchor
is
a
common
type
of
supporting
element
used
in
the
design and construction of in-situ
retaining walls. It is an installation that is
capable
of
transmitting
an
applied
tensile
load
to
a
load
bearing
stratum
which may be a soil
or rock. A summary about ground anchors will be
given
in this section. Types, capacity,
design, construction and quality control will
be reviewed.
3.1.2 Types and Capacity of Anchors
Temporary anchor and
permanent anchor are the main types and as the
names imply the former is used in
temporary works and usually a period of
maximum
two
years
are
assigned
as
the
design
life.
Design
life
of
a
permanent
anchor
is
the
same
as
the
life
of
structure.
Corrosion
protection
details and
factors of safety are the main differences between
the two types.
-
-
-
-
-
-
-
-
-
上一篇:(完整版)地质工程专业常用英文词汇
下一篇:建筑专业名词中英文对照.