关键词不能为空

当前您在: 主页 > 英语 >

地下室设计深基坑中英文对照外文翻译文献

作者:高考题库网
来源:https://www.bjmy2z.cn/gaokao
2021-02-05 19:14
tags:

-

2021年2月5日发(作者:平静)





中英文对照外文翻译




(


文档含英文原文和中文翻译


)



Deep Excavations



ABSTRACT




All


major


topics


in


the


design


of


in-situ


retaining


systems for deep excavations in urban areas are outlined. Type of wall, water


related problems and water pressures, lateral earth pressures, type of support,


solution


to


earth


retaining


walls,


types


of


failure,


internal


and


external


stability problems.


KEYWORDS


: deep excavation; retaining wall; earth pressure;




INTRODUCTION



Numbers


of


deep


excavation


pits


in


city


centers


are


increasing


every


year. Buildings, streets surrounding excavation locations and design of very


deep basements make excavations formidable projects. This chapter has been


organized in such a way that subjects related to deep excavation projects are


summarized in several sections in the order of design routine. These are types


of in-situ walls, water pressures and water related problems. Earth pressures


in cohesionless and cohesive soils are presented in two different categories.


Ground


anchors,


struts


and


nails


as


supporting


elements


are


explained.


Anchors are given more emphasis compared to others due to widespread use


observed in the recent


years. Stability of retaining systems are discussed as


internal


and


external


stability.


Solution


of


walls


for


shears,


moments,


displacements


and


support


reactions


under


earth


and


water


pressures


are


obtained making use of different methods of analysis. A pile wall supported


by anchors is solved by three methods and the results are compared. Type of


wall


failures,


observed


wall


movements


and


instrumentation


of


deep


excavation projects are summarized.



1. TYPES OF EARTH RETAINING WALLS



1.1 Introduction





More than several types of in-situ walls are used to support excavations.


The criteria for the selection of type of wall are size of excavation, ground


conditions,


groundwater


level,


vertical


and


horizontal


displacements


of


adjacent


ground


and


limitations


of


various


structures,


availability


of


construction, cost, speed of work and others. One of the main decisions is the


water-tightness


of


wall.


The


following


types


of


in-situ


walls


will


be


summarized below;




1. Braced walls, soldier pile and lagging walls



2. Sheet-piling or sheet pile walls



3. Pile walls (contiguous, secant)



4. Diaphragm walls or slurry trench walls



5. Reinforced concrete (cast-in-situ or prefabricated) retaining walls



6. Soil nail walls



7. Cofferdams



8. Jet-grout and deep mixed walls



9. Top-down construction



10. Partial excavation or island method



1.1.1 Braced Walls



Excavation proceeds step by step after placement of soldier piles or so


called


king


posts


around


the


excavation


at


about


2


to


3


m


intervals.


These


may be steel H, I or WF sections. Rail sections and timber are also used. At


each level horizontal waling beams and supporting elements (struts, anchors,



nails) are constructed. Soldier piles are driven or commonly placed in bored


holes


in


urban


areas,


and


timber


lagging


is


placed


between


soldier


piles


during the excavation. Various details of placement of lagging are available,


however,


precast


units,


in-situ


concrete


or


shotcrete


may


also


be


used


as


alternative


to


timber.


Depending


on


ground


conditions


no


lagging


may


be


provided in relatively shallow pits.



Historically


braced


walls


are


strut


supported.


They


had


been


used


extensively before the ground anchor technology was developed in 1970


?


s.


Soils with some cohesion and without water table are usually suitable for this


type of construction or dewatering is


accompanied if required and allowed.


Strut support is commonly preferred in narrow excavations for pipe laying or


similar


works


but


also


used


in


deep


and


large


excavations


(See


Fig


1.1).


Ground anchor support is increasingly used and preferred due to access


for


construction


works


and


machinery.


Waling


beams


may


be


used


or


anchors


may be placed directly on soldier piles without any beams.


1.1.2 Sheet-piling or Sheet Pile Walls



Sheet pile is a thin steel section (7-30 mm thick) 400-500 mm wide. It is


manufactured


in


different


lengths


and


shapes


like


U,


Z


and


straight


line


sections (Fig. 1.2). There are interlocking watertight grooves at the sides, and


they


are


driven


into


soil


by


hammering


or


vibrating.


Their


use


is


often


restricted


in


urbanized


areas


due


to


environmental


problems


like


noise


and


vibrations.


New


generation


hammers


generate


minimum


vibration


and



disturbance,


and


static


pushing


of


sections


have


been


recently


possible.


In


soft ground several sections may be driven using a template. The end product


is a watertight steel wall in soil. One side (inner) of wall is excavated step by


step


and


support


is


given


by


struts


or


anchor.


Waling


beams


(walers)


are


frequently used. They are usually constructed in water bearing soils.



Steel


sheet


piles


are


the


most


common


but


sometimes


reinforced


concrete


precast


sheet


pile


sections


are


preferred


in


soft


soils


if


driving


difficulties


are


not


expected.


Steel


piles


may


also


encounter


driving


difficulties in very dense, stiff soils or in soils with boulders. Jetting may be


accompanied during the process to ease penetration. Steel sheet pile sections


used in such difficult driving conditions are selected according to the driving


resistance rather than the design moments in the project. Another frequently


faced


problem


is


the


flaws


in


interlocking


during


driving


which


result


in


leakages


under


water


table.


Sheet


pile


walls


are


commonly


used


for


temporary


purposes


but


permanent


cases


are


also


abundant.


In


temporary


works sections are extracted after their service is


over,


and they


are reused


after


maintenance.


This


process


may


not


be


suitable


in


dense


urban


environment.


1.1.3 Pile Walls



In-situ pile retaining walls are very popular due to their availability and


practicability. There are different types of pile walls (Fig. 1.3). In contiguous


(intermittent)


bored


pile


construction,


spacing


between


the


piles


is


greater



than the diameter of piles. Spacing is decided based on type of soil and level


of design moments but it should not be too large, otherwise pieces of lumps


etc.


drop


and


extra


precautions


are


needed.


Cohesive


soils


or


soils


having


some


cohesion


are


suitable.


No


water


table


should


be


present.


Acceptable


amount of water is collected at the base and pumped out. Common diameters


are 0.60, 0.80, 1.00 m. Waling beams (usually called ?breasting beams


?


) are


Tangent


piles


with


grouting


in


between


are


used


when


secant


piling


or


diaphragm


walling


equipment


is


not


available


(i.e.


in


cases


where


ground


water exists). Poor workmanship creates significant problems.




Secant bored pile walls are formed by keeping spacing of piles less than


diameter


(S


It


is


a


watertight


wall


and


may


be


more


economical


compared


to


diaphragm


wall


in


small


to


medium


scale


excavations


due


to


cost of site operations and bentonite plant.


There


is


also


need


for


place


for


the


plant.


It


may


be


constructed


“hard


-


hard” as well as “soft


-


hard”. “Soft” concrete pile


contains low cement


content and some bentonite. Primary unreinforced piles are constructed first


and then reinforced secondary piles are formed by cutting the primary piles.


Pile construction methods may vary in different countries for all type of pile


walls


like


full


casing


support,


bentonite


support,


continuous


flight


auger


(CFA) etc. mostly reinforced concrete but sheet pile sections or steel beams


are also used.



1.1.4 Diaphragm Walls




Diaphragm wall provides structural support and water tightness. It is a


classical technique for many deep excavation projects, large civil engineering


works,


underground


car


parks,


metro


pits


etc.


especially


under


water


table.


These reinforced concrete diaphragm (continuous) walls are also called slurry


trench walls due to the reference given to the construction technique where


excavation of wall is made possible by filling and keeping the wall cavity full


with


bentonite-water


mixture


during


excavation


to


prevent


collapse


of


the


excavated vertical surfaces. Wall thickness varies between 0.50 m and 1.50 m.


The wall is constructed panel by panel in full lengths are 2 m to


10 m. Short lengths (2-2.5 m) are selected in unstable soils or under very high


surcharges.


Nowadays


depth


of


panels


water


stops


exceeded


100


m,


excavation


depths


exceeded


50


m.


Different


panel


shapes


other


than


the


conventional straight section like T, L, H, Y


, + are possible to form and used


for


special


purposes.


Panel


excavation


is


made


by


cable


or


kelly


supported


buckets


and by a recent


design


called ?cutter


?



or ?hydrofraise


?



which is a


pair of hydraulically operated rotating disks provided with hard cutting tools.


Excavation


in


rock


is


possible.


Slurry


wall


technique


is


a


specialized


technique


and


apart


from


the


bucket


or


the


frame


carrying


the


cutter


equipment


like


crawler


crane,


pumps,


tanks,


desanding


equipment,


air


lifts,


screens,


cyclones,


silos,


mixers,


extractor


are


needed.


Tremie


concrete


is


placed


in


the


slurry


starting


from


the


bottom


after


lowering


reinforcement



cages. Joint between the panels is a significant detail in water bearing soils


and steel pipe, H-beam or water stops are used.




1.1.5 Reinforced Concrete Retaining Walls Excavation in Stages



It


is


a


common


type


of


staged


excavation


wall


usually


supported


by


ground anchors. Soils with some cohesion are suitable because each stage is


first excavated before formwork and concrete placement. No water table or


appreciable amount of water should be present. Sometimes micropile support


is given if required due to expected cave-ins.




1.1.6 Soil Nail Walls



Similar to the method above excavation is made step by step (1.5 to 2 m


high). Shotcrete is common for facing and wiremesh is used. Soft facing is


also


possible


making


use


of


geotextiles.


Hole


is


drilled,


ordinary


steel


bars


are


lowered,


and


grout


is


placed


without


any


pressure.


Soil


should


be


somewhat


cohesive


and


no


water


table


or


significant


water


flow


should


be


present.



1.1.7 Cofferdams



Cofferdam


is


a


temporary


earth


retaining


structure


to


be


able


to


make


excavation for construction activities. It is usually preferred in the coastal and


sea environment like bridge piers and abutments in rivers, lakes etc., wharves,


quay


walls,


docks,


break


waters


and


other


structures


for


shore


protection,


large waterfront structures such as pump houses, subjected to heavy vertical


and horizontal loads. Sheet piling is commonly used in various forms other



than


conventional


walls


like


circular


cellular


bodies


or


double


walls


connected


inside


and


filled


with


sand.


Stability


is


maintained


by


sheeting


driven


deeper


than


base,


sand


body


between


sheeting


and


inside


tie


rods.


Earth embankments and concrete bodies are also used. Contiguous, tangent,


secant


piles


or


diaphragm


walls


are


constructed


in


circular


shapes,


and


no


internal


bracing


or


anchoring


is


used


to


form


a


cofferdam.


Reinforced


concrete


waling


beams


support


by


arching.


Shafts


are


also


made


with


this


method.



Large excavations or project details may require additional lateral


support.



1.1.8 Jet Grout and Deep Mixed Walls



Retaining walls are made by single to triple row of jet grout columns or


deep mixed columns. There is a soil mixed wall(SMW) technique specially


developed for wall construction where H sections are used for reinforcement.


Single


reinforcing


bar


is


placed


in


the


central


hole


opened


for


jet


grout


columns. Anchors, nails or struts may be used for support.



1.1.9 Top Down Construction



Retaining


structure


(generally


diaphragm


wall)


is


designed


and


constructed


as


permanent


load


bearing


walls


of


basement.


Piles


or


barettes


are similarly placed to complete the structural frame. Top slab is cast at the


ground surface level, and excavation is made under the slab by smaller sized


excavators and continued down forming basement slabs at each level. There


are


special


connection


details.


Top


down


method


is


preferred


in


highly



populated city centers where horizontal and vertical


displacements


are very


critical,


and


anchors


and


struts


are


very


difficult


to


use


due


to


complex


underground facilities and lifeline structures and site operations are difficult


to perform.



1.1.10 Partial Excavation or Island Method



It is possible to give strut support to retaining walls at a later stage after


constructing central sections of a building in large size excavations. Core of


the


structure


is


built


at


the


central


part


making


sloped


excavations


at


peripheral


areas


and


then


the


core


frame


is


used


to


give


support


to


walls


(Figure


1.9).


It


may


be


more


practical


and


construction


time


may


be


less


compared to conventional braced system. This method may not be suitable in


soft and weak soils due to stability and deformation problems during sloped


excavations.



2. EARTH PRESSURES ON IN- SITU RETAINING WALLS



2.1. Introduction




Earth pressures on in-situ retaining walls are rather different than those


on ordinary retaining walls due to the supporting elements. Free displacement


of


walls


are


not


allowed.


Type


of


support


affects


the


distribution


of


earth


pressure. Strut loads were measured in strutted excavations in many countries


in the past, and recommendations were given. Ground anchor technology is


relatively


new,


and


data


on


instrumented


anchored


walls


for


total


lateral



pressure


and


for


water


pressure


are


being


accumulated.


Earth


pressure


diagrams


on


strutted


and


anchored


walls


are


expected


to


be


somewhat


different


due


to


stiffer


support


conditions


in


the


former.


Theoretical


approaches will also be discussed.




2.2. Earth Pressure Distributions on Walls




Terzaghi


and


Peck


(1967)


and


Peck


(1969)


based


on


load


measurements on struts recommend the pressure distribution shown in Figure


2.1 for cohesionless soils. It is a uniform pressure and given by Eq. 2.1;




p = 0.65 K


A



γ


t


H















2.1




where K


A


is the active earth pressure coefficient, H is the height of wall.


Unit weight (γt) is described as the bulk unit weight


in the original references.


Since


braced


excavations


were


generally


dewatered


in


the


past


projects


the


unit


weight


in


the


expression


was


described


as


wet


or


bulk.


If


wall


is


watertight


and


water


table


is


present,


buoyant


unit


weight


should


be


used


under water table and water pressure should be added.




The rectangular diagram proposed in the figure is not an actual pressure


distribution


but


an


envelope


obtained


by


plotting


the


measured


strut


loads


converted to


pressure distribution at


each stage


of excavation including


the


final


depth


covering


all


distributions.


It


is


also


called


apparent


pressure


distribution.


It


is


regarded


as


a


conservative


approach


because


strut


loads


calculated by such an envelope are generally greater than the measured loads.



Rectang


ular envelope with



p = 0.2 γt H




is also recommended by Twine


and Roscoe (1996) based on more recent field measurements. Similarly use


of submerged unit weight below water table and addition of water pressure is


recommended. Data on cohesive soils are classified for soft to medium stiff


clays and stiff clay.



Anchor or nail supported walls may show higher lateral displacements,


and


stress


increases


at


the


upper


levels


of


walls


may


be


somewhat


less


compared


to


the


distributions


on


strutted


walls.


However,


there


are


no


documented comparisons. In the solution of anchored walls by finite element,


boundary


element,


finite


difference


softwares


or


simpler


spring


models


the


analyses may be repeated without assigning pre-tensions initially like in case


of


nail


supported


walls


and


then


assign


the


calculated


reactions


as


pre-tensions.


There are also recommendations on selection of the type of distribution


in


relation


to


height


of


braced


walls.


Distributions


based


on


pressure


cell


records


are


recommended


for


all


heights


but


distributions


by


strut


load


measurements are not found suitable for walls higher than 15 m, they may be


used for walls of 10



15 m height depending on conditions of the ground and


construction and recommended for heights less than 10 m.



Another common case is an alluvial profile where clay, silt, sand layers


mixed in different proportions lie in different thicknesses. If a dominant layer


is


present


one


of


the


above


distributions


may


be


selected,


otherwise


a



theoretical


approach


like


Coulomb’s


earth


pressure


expression


may


be


followed


making


use


of


effective


parameters,


submerged


unit


weights


and


added water pressure.



Effect of different surcharge loads on walls may be calculated by stress


distributions in elastic medium (e.g. NA


VFAC 1982). For the upper limit of


very rigid walls the distributions are doubled. Wide surcharge loads may also


be converted to equivalent heights of soil layer.



3. SUPPORTING ELEMENTS



3.1 Ground Anchors



3.1.1 Introduction



Ground


anchor


is


a


common


type


of


supporting


element


used


in


the


design and construction of in-situ retaining walls. It is an installation that is


capable


of


transmitting


an


applied


tensile


load


to


a


load


bearing


stratum


which may be a soil or rock. A summary about ground anchors will be given


in this section. Types, capacity, design, construction and quality control will


be reviewed.




3.1.2 Types and Capacity of Anchors



Temporary anchor and permanent anchor are the main types and as the


names imply the former is used in temporary works and usually a period of


maximum


two


years


are


assigned


as


the


design


life.


Design


life


of


a


permanent


anchor


is


the


same


as


the


life


of


structure.


Corrosion


protection


details and factors of safety are the main differences between the two types.

-


-


-


-


-


-


-


-



本文更新与2021-02-05 19:14,由作者提供,不代表本网站立场,转载请注明出处:https://www.bjmy2z.cn/gaokao/602989.html

地下室设计深基坑中英文对照外文翻译文献的相关文章