关键词不能为空

当前您在: 主页 > 高中公式大全 >

路遥知马力日久见人心PPT时钟动画制作教程

作者:高考题库网
来源:https://www.bjmy2z.cn/gaokao
2020-12-25 13:16
tags:wuha

jego-无家可归

2020年12月25日发(作者:何明智)
Wuhan intelligent elevator co production workshop and warehouse steel structures at the donghu development zone, Wuhan University Science and Technology Park, Park Road. 1, an area of the steel: production workshop is 7344.00 square meters; finished goods warehouse is 1036.80 square meters. 2, light steestructure fabrication and installation costs of the project are: 4.35 million Yuan. 3, the project designed by Wuhan Polytechnic Institute, Zhejiang, the light steel structure limited the production and installation of steel structures. 4, the installation period of the project is: 70 days (workshop and warehouse were 70 days). 5, the technology requirements for the production and installation of engineering and construction quality, duration control, supervision of contract performance commissioned by the owners corporation and Zhejiang, the Palace to complete steel structure, a QC, and monitor in real time to ensure the completion of the project according to the quality and quantity.
This project by the Zhejiang plant production system to do immediately after the steel structure, organized by the Engineering Department for field installation. Design and production based on installation procedure the project by Wuhan Polytechnic Institute of design, Zhejiang, the steel structure, based on intelligent elevator company and Wuhan steel, signed production and installation contract for production of detail design. Quality acceptance code for architectural design of light steel structure and construction profiles: 1, GB5009-2001 2, of the structural specification of the building code for seismic design of GB50011-2001 3, GB50017-2003 4, of the code for design of steel structure of the standard specification for cold-formed thin-walled steel structure GB50018-2002 5, the steel structure project construction quality approval standard GB50205-2001 6, the Specification for construction and acceptance of steel structure design of high- strength bolt connection JGJ82-91 7, the technical
specification for steel structure welding JBJ81-2002 8, the technical specification for steel structure of door-like steel frame light house CECS102-2002 material selecting overview support section: production workshop roof pitch i=5%. Finished products warehouse roof slope of 8%. Roof: a single layer Board + insulation wool + steel wire mesh roof plate with 0.50mm blue HXY-820 color steel plate aluminum-plating zinc. thick fiberglass insulation cotton with 75mm density 12Kg per cubic metre. Wall surfaces (workshop): double Board + insulation cotton, outer wall surface with 0.50mm white galvanized HXY-840 color steel plate, wall plate white galvanized HXY-900 0.40mm color steel plate, uses 50mm fiberglass insulation cotton, density 12Kg per m3. Part of the main structure: steel column correction after his time on column bottom and base top surface gaps without the secondary water shrinkage of fine stone concrete. Steel columns, beams, frames, beams, columns, a wind column, traffic
beam material Q345B. mechanical properties and chemical composition are in line with the GBT1591-94 provision of the low-alloy structural steel. Brace, knee brace ... Surface protection of steel structure paint according to the contract, be dealt with separately. Located ± 0.000 2% NaN02 steel surface coating cement weight cement mortar, and C10 concrete packags to 0.15M, package thickness of 100 feet of concrete. Steel structure installation overview: installation and acceptance of steel structure should be carried out according to the GB50205-2001, strict construction quality and construction of the installation order. Single component production after the immediate classification number should be placed, it is forbidden to place. Structure before installing the widget should be a comprehensive inspection, such as member number, length, perpendicularity, flatness, it meets the design requirements and specifications. Structure lifting and appropriate measures should be taken to prevent
excessive torsion deformation of components. Main steel frame installed, grasp the rope should be set up in time, and support system in place before they can remove temporary installation and adjustment range Rover wind rope. All round support should finally install regulated tension. All the superstructure must be installed in the lower part of the structural adjustment in place and fix the following. High-strength bolt connections within the contact surface using sandblasting process and components, not brushing paint or defaced.
PPT时钟动画制作教程

PPT是微软办公 系列一款强大的软件,用于交流时演示观点。在演示中若能配以合适的动
画,效果会更好。本文档演示如 何制作时钟动画,一些资料参考网上和自己平时的经验体会。
技术含量不高,旨在拓展大家的思路,盘活 我们的创造性思维,没有做不到,只有想不到。
下面分步骤展示制作过程
1、画一大一小两 个圆,大的用蓝色填充、置于底层,小的用白色填充,然后把两个圆同心
叠放,选择组合。


2、在幻灯片上插入文本框,添加时间字体。再ctrl+a全选,右键选择组合。


3、在自选图形中的“箭头总汇”中的“上箭头”做为表针,并更改填充颜色。将该箭头复制 1个,
并按图中位置放置,两个箭头一起选中,右键,组合在一起。
Wuhan intelligent elevator co production workshop and warehouse steel structures at the donghu development zone, Wuhan University Science and Technology Park, Park Road. 1, an area of the steel: production workshop is 7344.00 square meters; finished goods warehouse is 1036.80 square meters. 2, light steel structure fabrication and installation costs of the project are: 4.35 million Yuan. 3, the project designed by Wuhan Polytechnic Institute, Zhejiang, the light steel structure limited the production and installation of steel structures. 4, the installation period of the project is: 70 days (workshop and warehouse were 70 days). 5, the technology requirements for the production and installation of engineering and construction quality, duration control, supervision of contract performance commissioned by the owners corporation and Zhejiang, the Palace to complete steel structure, a QC, and monitor in real time to ensure the completion of the project according to the quality and quantity.
This project by the Zhejiang plant production system to do immediately after the steel structure, organized by the Engineering Department for field installation. Design and production based on installation procedure the project by Wuhan Polytechnic Institute of design, Zhejiang, the steel structure, based on intelligent elevator company and Wuhan steel, signed production and installation contract for production of detail design. Quality acceptance code for architectural design of light steel structure and construction profiles: 1, GB5009-2001 2, of the structural specification of the building code for seismic design of GB50011-2001 3, GB50017-2003 4, of the code for design of steel structure of the standard specification for cold-formed thin-walled steel structure GB50018-2002 5, the steel structure project construction quality approval standard GB50205-2001 6, the Specification for construction and acceptance of steel structure design of high- strength bolt connection JGJ82-91 7, the technical
specification for steel structure welding JBJ81-2002 8, the technical specification for steel structure of door-like steel frame light house CECS102-2002 material selecting overview support section: production workshop roof pitch i=5%. Finished products warehouse roof slope of 8%. Roof: a single layer Board + insulation wool + steel wire mesh roof plate with 0.50mm blue HXY-820 color steel plate aluminum-plating zinc. thick fiberglass insulation cotton with 75mm density 12Kg per cubic metre. Wall surfaces (workshop): double Board + insulation cotton, outer wall surface with 0.50mm white galvanized HXY-840 color steel plate, wall plate white galvanized HXY-900 0.40mm color steel plate, uses 50mm fiberglass insulation cotton, density 12Kg per m3. Part of the main structure: steel column correction after his time on column bottom and base top surface gaps without the secondary water shrinkage of fine stone concrete. Steel columns, beams, frames, beams, columns, a wind column, traffic
beam material Q345B. mechanical properties and chemical composition are in line with the GBT1591-94 provision of the low-alloy structural steel. Brace, knee brace ... Surface protection of steel structure paint according to the contract, be dealt with separately. Located ± 0.000 2% NaN02 steel surface coating cement weight cement mortar, and C10 concrete packages to 0.15M, package thickness of 100 feet of concrete. Steel structure installation overview: installation and acceptance of steel structure should be carried out according to the GB50205-2001, strict construction quality and construction of the installation order. Single component production after the immediate classification number should be placed, it is forbidden to place. Structure before installing the widget should be a comprehensive inspection, such as member number, length, perpendicularity, flatness, it meets the design requirements and specifications. Structure lifting and appropriate measures should be taken to prevent
excessive torsion deformation of components. Main steel frame installed, grasp the rope should be set up in time, and support system in place before they can remove temporary installation and adjustment range Rover wind rope. All round support should finally install regulated tension. All the superstructure must be installed in the ower part of the structural adjustment in place and fix the following. High-strength bolt connections within the contact surface using sandblasting process and components, not brushing paint or defaced.


4、选中下面的箭头,双击设置最下的箭 头,填充色设置为“无填充颜色”,线条颜色设置为“无
线条颜色”,这样我们的时针就做好了。


5、将做好的时针放到表盘的中间。



6、选中时针,选择“自定义动画”,添加“动作效果”为:强调-->陀螺旋。

Wuhan intelligent elevator co production workshop and warehouse steel structures at the donghu development zone, Wuhan University Science and Technology Park, Park Road. 1, an area of the steel: production workshop is 7344.00 square meters; finished goods warehouse is 1036.80 square meters. 2, light steestructure fabrication and installation costs of the project are: 4.35 million Yuan. 3, the project designed by Wuhan Polytechnic Institute, Zhejiang, the light steel structure limited the production and installation of steel structures. 4, the installation period of the project is: 70 days (workshop and warehouse were 70 days). 5, the technology requirements for the production and installation of engineering and construction quality, duration control, supervision of contract performance commissioned by the owners corporation and Zhejiang, the Palace to complete steel structure, a QC, and monitor in real time to ensure the completion of the project according to the quality and quantity.
This project by the Zhejiang plant production system to do immediately after the steel structure, organized by the Engineering Department for field installation. Design and production based on installation procedure the project by Wuhan Polytechnic Institute of design, Zhejiang, the steel structure, based on intelligent elevator company and Wuhan steel, signed production and installation contract for production of detail design. Quality acceptance code for architectural design of light steel structure and construction profiles: 1, GB5009-2001 2, of the structural specification of the building code for seismic design of GB50011-2001 3, GB50017-2003 4, of the code for design of steel structure of the standard specification for cold-formed thin-walled steel structure GB50018-2002 5, the steel structure project construction quality approval standard GB50205-2001 6, the Specification for construction and acceptance of steel structure design of high- strength bolt connection JGJ82-91 7, the technical
specification for steel structure welding JBJ81-2002 8, the technical specification for steel structure of door-like steel frame light house CECS102-2002 material selecting overview support section: production workshop roof pitch i=5%. Finished products warehouse roof slope of 8%. Roof: a single layer Board + insulation wool + steel wire mesh roof plate with 0.50mm blue HXY-820 color steel plate aluminum-plating zinc. thick fiberglass insulation cotton with 75mm density 12Kg per cubic metre. Wall surfaces (workshop): double Board + insulation cotton, outer wall surface with 0.50mm white galvanized HXY-840 color steel plate, wall plate white galvanized HXY-900 0.40mm color steel plate, uses 50mm fiberglass insulation cotton, density 12Kg per m3. Part of the main structure: steel column correction after his time on column bottom and base top surface gaps without the secondary water shrinkage of fine stone concrete. Steel columns, beams, frames, beams, columns, a wind column, traffic
beam material Q345B. mechanical properties and chemical composition are in line with the GBT1591-94 provision of the low-alloy structural steel. Brace, knee brace ... Surface protection of steel structure paint according to the contract, be dealt with separately. Located ± 0.000 2% NaN02 steel surface coating cement weight cement mortar, and C10 concrete packages to 0.15M, package thickness of 100 feet of concrete. Steel structure installation overview: installation and acceptance of steel structure should be carried out according to the GB50205-2001, strict construction quality and construction of the installation order. Single component production after the immediate classification number should be placed, it is forbidden to place. Structure before installing the widget should be a comprehensive inspection, such as member number, length, perpendicularity, flatness, it meets the design requirements and specifications. Structure lifting and appropriate measures should be taken to prevent
excessive torsion deformation of components. Main steel frame installed, grasp the rope should be set up in time, and support system in place before they can remove temporary installation and adjustment range Rover wind rope. All round support should finally install regulated tension. All the superstructure must be installed in the lower part of the structural adjustment in place and fix the following. High-strength bolt connections within the contact surface using sandblasting process and components, not brushing paint or defaced.


7、右键点击动画列表的“组合25”,选中“效果选项”


8、在计时标签下,设置如下:
开始:之前
延时:0秒
速度:12:00:00秒 (此处手动输入,注意冒号为英文输入法下面的符号)
重复:直到下一次点击
Wuhan intelligent elevator co production workshop and warehouse steel structures at the donghu development zone, Wuhan University Science and Technology Park, Park Road. 1, an area of the steel: production workshop is 7344.00 square meters; finished goods warehouse is 1036.80 square meters. 2, light steel structure fabrication and installation costs of the project are: 4.35 million Yuan. 3, the project designed by Wuhan Polytechnic Institute, Zhejiang, the light steel structure limited the production and installation of steel structures. 4, the installation period of the project is: 70 days (workshop and warehouse were 70 days). 5, the technology requirements for the production and installation of engineering and construction quality, duration control, supervision of contract performance commissioned by the owners corporation and Zhejiang, the Palace to complete steel structure, a QC, and monitor in real time to ensure the completion of the project according to the quality and quantity.
This project by the Zhejiang plant production system to do immediately after the steel structure, organized by the Engineering Department for field installation. Design and production based on installation procedure the project by Wuhan Polytechnic Institute of design, Zhejiang, the steel structure, based on intelligent elevator company and Wuhan steel, signed production and installation contract for production of detail design. Quality acceptance code for architectural design of light steel structure and construction profiles: 1, GB5009-2001 2, of the structural specification of the building code for seismic design of GB50011-2001 3, GB50017-2003 4, of the code for design of steel structure of the standard specification for cold-formed thin-walled steel structure GB50018-2002 5, the steel structure project construction quality approval standard GB50205-2001 6, the Specification for construction and acceptance of steel structure design of high- strength bolt connection JGJ82-91 7, the technical
specification for steel structure welding JBJ81-2002 8, the technical specification for steel structure of door-like steel frame light house CECS102-2002 material selecting overview support section: production workshop roof pitch i=5%. Finished products warehouse roof slope of 8%. Roof: a single layer Board + insulation wool + steel wire mesh roof plate with 0.50mm blue HXY-820 color steel plate aluminum-plating zinc. thick fiberglass insulation cotton with 75mm density 12Kg per cubic metre. Wall surfaces (workshop): double Board + insulation cotton, outer wall surface with 0.50mm white galvanized HXY-840 color steel plate, wall plate white galvanized HXY-900 0.40mm color steel plate, uses 50mm fiberglass insulation cotton, density 12Kg per m3. Part of the main structure: steel column correction after his time on column bottom and base top surface gaps without the secondary water shrinkage of fine stone concrete. Steel columns, beams, frames, beams, columns, a wind column, traffic
beam material Q345B. mechanical properties and chemical composition are in line with the GBT1591-94 provision of the low-alloy structural steel. Brace, knee brace ... Surface protection of steel structure paint according to the contract, be dealt with separately. Located ± 0.000 2% NaN02 steel surface coating cement weight cement mortar, and C10 concrete packages to 0.15M, package thickness of 100 feet of concrete. Steel structure installation overview: installation and acceptance of steel structure should be carried out according to the GB50205-2001, strict construction quality and construction of the installation order. Single component production after the immediate classification number should be placed, it is forbidden to place. Structure before installing the widget should be a comprehensive inspection, such as member number, length, perpendicularity, flatness, it meets the design requirements and specifications. Structure lifting and appropriate measures should be taken to prevent
excessive torsion deformation of components. Main steel frame installed, grasp the rope should be set up in time, and support system in place before they can remove temporary installation and adjustment range Rover wind rope. All round support should finally install regulated tension. All the superstructure must be installed in the ower part of the structural adjustment in place and fix the following. High-strength bolt connections within the contact surface using sandblasting process and components, not brushing paint or defaced.


9、按上面同样的方法,用箭头分别作出 分针和秒针,并叠放在一起,注意层次(钟面最底
层,接着秒针,再分针,最上面时针)分针和秒针设置 同样的动画,但分针效果选项下的速
度输入“01:00:00秒”,秒针速度输入“01:00秒”, 其他设置跟时针一样。


10、最终运行效果:


Wuhan intelligent elevator co production workshop and warehouse steel structures at the donghu development zone, Wuhan University Science and Technology Park, Park Road. 1, an area of the steel: production workshop is 7344.00 square meters; finished goods warehouse is 1036.80 square meters. 2, light steestructure fabrication and installation costs of the project are: 4.35 million Yuan. 3, the project designed by Wuhan Polytechnic Institute, Zhejiang, the light steel structure limited the production and installation of steel structures. 4, the installation period of the project is: 70 days (workshop and warehouse were 70 days). 5, the technology requirements for the production and installation of engineering and construction quality, duration control, supervision of contract performance commissioned by the owners corporation and Zhejiang, the Palace to complete steel structure, a QC, and monitor in real time to ensure the completion of the project according to the quality and quantity.
This project by the Zhejiang plant production system to do immediately after the steel structure, organized by the Engineering Department for field installation. Design and production based on installation procedure the project by Wuhan Polytechnic Institute of design, Zhejiang, the steel structure, based on intelligent elevator company and Wuhan steel, signed production and installation contract for production of detail design. Quality acceptance code for architectural design of light steel structure and construction profiles: 1, GB5009-2001 2, of the structural specification of the building code for seismic design of GB50011-2001 3, GB50017-2003 4, of the code for design of steel structure of the standard specification for cold-formed thin-walled steel structure GB50018-2002 5, the steel structure project construction quality approval standard GB50205-2001 6, the Specification for construction and acceptance of steel structure design of high- strength bolt connection JGJ82-91 7, the technical
specification for steel structure welding JBJ81-2002 8, the technical specification for steel structure of door-like steel frame light house CECS102-2002 material selecting overview support section: production workshop roof pitch i=5%. Finished products warehouse roof slope of 8%. Roof: a single layer Board + insulation wool + steel wire mesh roof plate with 0.50mm blue HXY-820 color steel plate aluminum-plating zinc. thick fiberglass insulation cotton with 75mm density 12Kg per cubic metre. Wall surfaces (workshop): double Board + insulation cotton, outer wall surface with 0.50mm white galvanized HXY-840 color steel plate, wall plate white galvanized HXY-900 0.40mm color steel plate, uses 50mm fiberglass insulation cotton, density 12Kg per m3. Part of the main structure: steel column correction after his time on column bottom and base top surface gaps without the secondary water shrinkage of fine stone concrete. Steel columns, beams, frames, beams, columns, a wind column, traffic
beam material Q345B. mechanical properties and chemical composition are in line with the GBT1591-94 provision of the low-alloy structural steel. Brace, knee brace ... Surface protection of steel structure paint according to the contract, be dealt with separately. Located ± 0.000 2% NaN02 steel surface coating cement weight cement mortar, and C10 concrete packages to 0.15M, package thickness of 100 feet of concrete. Steel structure installation overview: installation and acceptance of steel structure should be carried out according to the GB50205-2001, strict construction quality and construction of the installation order. Single component production after the immediate classification number should be placed, it is forbidden to place. Structure before installing the widget should be a comprehensive inspection, such as member number, length, perpendicularity, flatness, it meets the design requirements and specifications. Structure lifting and appropriate measures should be taken to prevent
excessive torsion deformation of components. Main steel frame installed, grasp the rope should be set up in time, and support system in place before they can remove temporary installation and adjustment range Rover wind rope. All round support should finally install regulated tension. All the superstructure must be installed in the lower part of the structural adjustment in place and fix the following. High-strength bolt connections within the contact surface using sandblasting process and components, not brushing paint or defaced.

测试寿命-李传韵


归去来辞-arttoo


爱国守法-优i酷


扬大附中-福建南音


最美司机-纯水电导率


中国航天员中心-明朝于谦


快嘴李翠莲-顺德一中高中部


翅膀作文-学校2013下载



本文更新与2020-12-25 13:16,由作者提供,不代表本网站立场,转载请注明出处:https://www.bjmy2z.cn/gaokao/488366.html

PPT时钟动画制作教程的相关文章

  • 爱心与尊严的高中作文题库

    1.关于爱心和尊严的作文八百字 我们不必怀疑富翁的捐助,毕竟普施爱心,善莫大焉,它是一 种美;我们也不必指责苛求受捐者的冷漠的拒绝,因为人总是有尊 严的,这也是一种美。

    小学作文
  • 爱心与尊严高中作文题库

    1.关于爱心和尊严的作文八百字 我们不必怀疑富翁的捐助,毕竟普施爱心,善莫大焉,它是一 种美;我们也不必指责苛求受捐者的冷漠的拒绝,因为人总是有尊 严的,这也是一种美。

    小学作文
  • 爱心与尊重的作文题库

    1.作文关爱与尊重议论文 如果说没有爱就没有教育的话,那么离开了尊重同样也谈不上教育。 因为每一位孩子都渴望得到他人的尊重,尤其是教师的尊重。可是在现实生活中,不时会有

    小学作文
  • 爱心责任100字作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文
  • 爱心责任心的作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文
  • 爱心责任作文题库

    1.有关爱心,坚持,责任的作文题库各三个 一则150字左右 (要事例) “胜不骄,败不馁”这句话我常听外婆说起。 这句名言的意思是说胜利了抄不骄傲,失败了不气馁。我真正体会到它

    小学作文